Free Scrum SMC Practice Exam with Questions & Answers | Set: 5

Questions 41

One of the responsibilities of the Scrum Master is to facilitate timely identification of all risks faced by the

Scrum Team. As the Scrum Master for a team working on a banking application project, which of the following

techniques would you suggest for comprehensive risk identification?

Options:
A.

Risk Appetite.

B.

Probability Impact Grid.

C.

Risk Checklists.

D.

Risk Meeting.

Scrum SMC Premium Access
Questions 42

Scrum Master is the 'servant leader' of Scrum Team. In this context, which of the following is a key

responsibility of the Scrum Master?

Options:
A.

Help create Project Vision Statement

B.

Identify key stakeholders of the project

C.

Ensure back-up resources are available

D.

Define Acceptance Criteria for User Stories

Questions 43

The Scrum Master coordinates with the Product Owner and other stakeholders to ensure benefits from the

project are realized. Which of the following is true about Benefits Realization?

Options:
A.

Benefits from Scrum projects are realized during Demonstrate and Validate Sprint, Conduct Release

Planning, Create Deliverables and Retrospect Sprint processes.

B.

Benefits from Scrum projects are realized during Demonstrate and Validate Sprint, Retrospect Sprint, Ship

Deliverables and Retrospect Project processes.

C.

Benefits from Scrum projects are realized during Demonstrate and Validate Project, Retrospect Sprint,

Grooming Product Backlog and Retrospect Project processes.

D.

Benefits from Scrum projects are realized during Demonstrate and Validate Project, Conduct Release

Planning, Verify Deliverables and Retrospect Sprint processes.

Questions 44

As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of

Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this

regard?

Options:
A.

It is advisable to consider the Release Dates for the overall product or service to determine the Length of

Sprint.

B.

The impact and frequency of expected changes do not have any impact on the decision related to the

Length of Sprint.

C.

If the project is stable, with only minor changes expected, the Length of Sprint should be relatively shorter,

1 to 3 weeks.

D.

To get maximum benefits from a Scrum project, it is always recommended to keep the Sprint Time-boxed

to 6 weeks.