Questions 11

With reference to WBS scheduling, which of the following statements are FALSE?

Please choose the correct answer.

Response:

Options:
A.

In WBS scheduling, the activities which are assigned to the selected WBS elements are scheduled. In network scheduling on the other hand, all activities which belong to the network are scheduled.

B.

If you selected scheduling type 'WBS determines dates', the earliest start date of the activities is defaulted from the respective WBS elements in case of forward scheduling (or the latest finish date of the activities in case of backward scheduling).

C.

The execution of WBS scheduling consists of 2 steps: 1. Determining the initial dates (start dates for forward scheduling or finish dates for backward scheduling). 2. Transferring the dates of the activities into respective network headers and WBS elements.

D.

Activities which are not scheduled, but have relationships to activities involved in scheduling, are viewed as external activities. In this case, the dates of the external activity are taken into account as restricting dates.

SAP C_TPLM22_67 Premium Access
Questions 12

How can material components be assigned to network activities?

There are 3 correct answers to this question.

Response:

Options:
A.

By assigning them manually

B.

Using the bill of materials transfer

C.

Using assigned sales orders

D.

Using ProMan

E.

Using the Internet-based catalog

Questions 13

In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.

How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

Please choose the correct answer.

Response:

Options:
A.

The costs are distributed evenly over the earliest dates in the activity

B.

The system uses the key from the work center

C.

System uses valuation variant

D.

Costing key is considered

Questions 14

In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?

There are 3 correct answers to this question.

Response:

Options:
A.

This assignment can then be used to display the planned costs of the orders of the project

B.

This assignment can then be used to display the unit costs of the orders of the project

C.

It can be copied to a new project

D.

Cost planning can be moved automatically along with the activities

Questions 15

Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?

Please choose the correct answer.

Response:

Capacity planning board

Options:
A.

Work center planning board

B.

Project planning board

C.

Workforce planning board

Questions 16

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

Response:

Options:
A.

The system status created is active.

B.

The system status master data locked is activate.

C.

You are not the responsible person for that WBS element.

D.

The confirmation exceeds the budget assigned to the WBS.

Questions 17

Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?

Please choose the correct answer.

Response:

Options:
A.

Stock item

B.

Network item

C.

Non-stock item

D.

Procurement item

Questions 18

Which of the following determines the item category assigned in the sales documents?

There are 2 correct answers to this question.

Response:

Options:
A.

Sales document type

B.

Schedule line items

C.

Material pricing group

D.

Material item category group

Questions 19

Which type of billing is generally used in plant engineering and construction projects?

Please choose the correct answer.

Response:

Options:
A.

Periodic billing

B.

Project billing

C.

Milestone billing

D.

Fixed billing

Questions 20

In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this information?

Please choose the correct answer.

Response:

Options:
A.

You can enter in an apportionment reason

B.

You can enter in reason code

C.

You can enter in reference code

D.

You can enter in reason for rejection

Exam Code: C_TPLM22_67
Certification Provider: SAP
Exam Name: SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Last Update: Jul 10, 2025
Questions: 165

SAP Related Exams

How to pass SAP C_TFIN52_67 - SAP Certified Application Associate - Financial Accounting with SAP ERP 6.0 EhP7 Exam
How to pass SAP C_TFIN22_67 - SAP Certified Application Associate - Management Accounting with SAP ERP 6.0 EhP7 Exam
How to pass SAP C_TPLM30_67 - SAP Certified Application Associate - SAP Maintenance & Repair with ERP 6.0 EHP7 Exam
How to pass SAP C_TPLM40_65 - SAP Certified Application Associate - Quality Management with SAP ERP 6.0 EHP5 Exam
How to pass SAP C_TSCM62_67 - SAP Certified Application Associate - Sales and Distribution, ERP 6.0 EhP7 Exam
How to pass SAP C_SMPADM_30 - SAP Certified Application Associate - SAP Mobile Platform Native and Hybrid Application Administration (SMP 3.0) Exam
How to pass SAP C_BYD15_1908 - SAP Certified Application Associate - SAP Business ByDesign Implementation Consultant Exam
How to pass SAP C_C4H520_02 - SAP Certified Application Associate - SAP Field Service Management 2005 Exam
How to pass SAP C_S4PPM_1909 - SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management Exam
How to pass SAP C_TS410_2020 - SAP Certified Application Associate - Business Process Integration with SAP S/4HANA 2020 Exam
How to pass SAP C_C4H510_04 - SAP Certified Application Associate - SAP Service Cloud 2011 Exam
How to pass SAP C_C4H420_13 - SAP Certified Application Associate - SAP CPQ Implementation Exam
How to pass SAP C_BW4HANA_27 - SAP Certified Application Associate - Reporting, Modeling and Data Acquisition with SAP BW/4HANA 2.x Exam
How to pass SAP C_BRSOM_2020 - SAP Certified Application Associate - SAP Billing and Revenue Innovation Mgmt. - Subscription Order Management Exam
How to pass SAP C_BRU2C_2020 - SAP Certified Application Associate - SAP Billing and Revenue Innovation Management - Usage to Cash Exam

SAP Free Exams

SAP Free Exams
Examstrack provides free SAP exam prep materials and practice tests to support your SAP certification goals.