Free PRINCE2 Prince2-Practitioner Practice Exam with Questions & Answers | Set: 4

Questions 31

Which principle is supported by the activity Evaluate the Project?

Options:
A.

Continued Business Justification

B.

Defined roles and responsibilities

C.

Learn from experience

D.

Manage by stages

Questions 32

Which of the following activities could trigger the production of an exception plan?

Options:
A.

Review Stage status

B.

Giving ad hoc direction

C.

Escalating a project issue

D.

Report stage end

Questions 33

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

    Design for each month - correctly showing at public holidays and new company logo

    Selected photographs- 12 professionally-produced photographs, showing different members of staff

    Selected paper and selected envelope - for printing and mailing the calendar

    Chosen label design - a competition to design a label will be held as part of this project

    List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

    Create the customer fast using information from the Accounts and Marketing departments

    Confirm compliance with the Data Protection Legislation

    Create a design for each month - this will be done by the internal creative team

    Select and appoint a professional photographer

    Gather photograph design ideas from previous project and agree photographic session schedule

    Prepare a production cost forecast

    Select paper and envelope.

Stage 3 will include the activities to:

    Produce and select tie professionally-taken photographs

    Hold the label design competition and choose the label design

    Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

Options:
A.

The tolerances stated in the Project Plan CANNOT be changed.

B.

The Executive needs to seek formal approval from corporate management to implement this change.

C.

The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.

D.

The revision of the Project Plan would have to wait until the end stage assessment of stage 2.

Questions 34

Which of the following statements is FALSE regarding the Continued Business Justification?

Options:
A.

The justification for the project must remain the same throughout the project.

B.

The justification for the project should remain vabd.

C.

The justification for the project may change.

D.

If the project is no longer justified it should be stopped.

Questions 35

When updating the project plan as part of Managing a stage boundary, what else might be updated?

Options:
A.

Exception Plan

B.

Project Management team

C.

Business Case

D.

Project Initiation Documentation

Questions 36

Additional Information

Prince2-Practitioner Question 36

Further information on some resources who could be involved in the project:

Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.

Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.

Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.

Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about roles on the Outsourcing project.

Prince2-Practitioner Question 36

Options:
Questions 37

Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

Options:
A.

Project Assurance

B.

Project Manager

C.

Corporate or Programme Management

D.

Project Support

Questions 38

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.

Which 2 statements explain why the Marketing Director should be appointed as the Executive for this project?

Options:
A.

She has been with the company for three years.

B.

She previously had a successful career in publicity.

C.

She is able to represent the business needs of MNO Manufacturing.

D.

She has authority to commit the marketing budget, from which the project will be funded.

E.

She requires more experience working with the engineering industry.

Questions 39

Which of the following roles cannot be combined?

Options:
A.

Executive and Senior User

B.

Project Manager and Project Support

C.

Project Assurance and Team Manager

D.

Senior Suppler and Supplier Assurance

Questions 40

Scenario

Additional Information

Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.

Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.

Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.

Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.

Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.

Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet been decided which of the photographers to use.

Which 2 statements explain why the CEO should be appointed as the Executive for this project?

Options:
A.

He started the company 25 years ago.

B.

He knows his job very well.

C.

He restricts his visits to the engineering area.

D.

He has the authority to commit resources as required.

E.

He has an overall perspective of the business's strategic requirements.