Free PRINCE2 PRINCE2-7-Practitioner Practice Exam with Questions & Answers

Questions 1

During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.

Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?

Options:
A.

Define roles, responsibilities and relationships, because the project is actively engaging and communicating with an external stakeholder group

B.

Define roles, responsibilities and relationships, because the Sustainability Manager must be the sole spokesperson for every project communication

C.

Tailor to suit the project, because every large project is required to communicate through a local newspaper

D.

Tailor to suit the project, because the Portfolio Director is personally accountable for preparing all stakeholder communications

PRINCE2 PRINCE2-7-Practitioner Premium Access
Questions 2

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:
A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Questions 3

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:
A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project

B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package

C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options

D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working

Questions 4

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:
A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Questions 5

BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.

Is this an appropriate application of the plans practice, and why?

Options:
A.

Yes, because the specialist supplier should own the stage plan whenever it delivers most of the stage products, and team managers can prepare the relevant information

B.

Yes, because the project manager should prepare stage plans only for stages involving more than one supplier

C.

No, because each external supplier should prepare the complete stage plan for the stage in which it works

D.

No, because the project manager remains responsible for preparing each stage plan; team managers may prepare team plans and detailed work package information

Questions 6

At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.

Which practice is being applied in ‘managing a stage boundary’?

Options:
A.

Plans

B.

Organization

C.

Quality

D.

Progress

Questions 7

At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.

Which practice is being applied?

Options:
A.

Business case

B.

Plans

C.

Progress

D.

Quality

Questions 8

BUSINESS CASE

Here are three statements related to the ‘business case’ practice.

In which management product should each statement be recorded?

Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.

Options:
A.

Business case

B.

Benefits management approach

C.

Sustainability management approach

D.

End stage report

E.

Project brief

F.

Commercial management approach

Statement 1:

The project will use a linear-sequential delivery method, and a reputable external supplier will deliver most of the specialist work.

Statement 2:

One sustainability target is to reduce the number of visitors arriving in internal-combustion vehicles. The Chief Technology Officer will implement monitoring technology, and the Business Opportunities Director will

Questions 9

BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.

Why is this an appropriate application of the ‘confirm project acceptance’ activity?

Options:
A.

Because the project manager should complete the end project performance assessment before any supplier demobilizes

B.

Because the project manager should arrange a celebration before the contractor leaves the site

C.

Because all project information should be archived before the completed project product is accepted

D.

Because the project manager should confirm that handover to the operational and maintenance environment is complete

Questions 10

While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:
A.

Yes, because a stage boundary may be aligned with an important external decision point, such as a funding approval

B.

Yes, because every stage may end immediately after one specialist product has been completed and funding has been approved

C.

No, because stage length must be determined solely by the level of risk

D.

No, because stage length must be determined by the technical complexity of the work

Certification Provider: PRINCE2
Exam Name: PRINCE2 Project Management Practitioner (Version 7)
Last Update: Oct 3, 2026
Questions: 56
PDF + Testing Engine
$164.99
$41.25
Testing Engine
$124.99
$31.25
PDF (Q&A)
$104.99
$26.25