During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.
Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
BuildyBrick’s planning specialist suggests that the project manager should prepare stage plans only for stages 2 and 4, while BuildyBrick should prepare the stage plans for stages 3 and 5 because suppliers will deliver most of the work.
Is this an appropriate application of the plans practice, and why?
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor’s account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in ‘managing a stage boundary’?
At project closure, the project manager prepares the end project report, noting that the project exceeded its budget by 10% and planned duration by 15% because of additional heritage protection work. The findings are summarized for the project board and shared with the LOB Portfolio Director so that other projects can learn from them.
Which practice is being applied?
BUSINESS CASE
Here are three statements related to the ‘business case’ practice.
In which management product should each statement be recorded?
Choose only ONE management product for each statement. Each management product can be used once, more than once, or not at all.
BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council’s operations and facilities teams are ready to receive, operate and maintain the completed centre.
Why is this an appropriate application of the ‘confirm project acceptance’ activity?
While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council’s financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council’s annual budget process.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
|
PDF + Testing Engine
|
|---|
|
$41.25 |
|
Testing Engine
|
|---|
|
$31.25 |
|
PDF (Q&A)
|
|---|
|
$26.25 |
PRINCE2 Free Exams |
|---|
|