Free PRINCE2 Prince2-Practitioner Practice Exam with Questions & Answers | Set: 2

Questions 11

Scenario

Extract from the Project Product Description (with errors)

Prince2-Practitioner Question 11

Which 2 statements apply to the Development skills required section?

Options:
A.

Move entry 13 to Composition because the appointment of the photographer is within the scope of this project.

B.

Move entry 13 to Derivation because this is a source of information for this project.

C.

Delete entry 14 because this skill is NOT required within this project.

D.

Delete entry 15 because this skill is NOT required within this project.

E.

Add 'Knowledge of Data Protection Act.

Questions 12

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:

Options:
A.

Project manager

B.

Project support

C.

Team Manager

D.

Project Assurance

Questions 13

Scenario

Additional Information

Product Description

Prince2-Practitioner Question 13

Quality notes from the Daily Log

The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.

The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.

MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.

All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.

Extract from the draft Quality Management Strategy (may contain errors)

Introduction

1. This document defines the approach to be taken to achieve the required quality levels during the project.

2. The Project Board will have overall responsibility for the Quality Management Strategy.

3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.

Quality management procedure - Quality standards

4. The selected service provider will operate to industry standards for providing outsourced services.

5. MFH document standards will be used.

Records

6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.

7. Configuration Item Records will be maintained for each product to describe its status, version and variant.

8. Approval records for products that require them will be stored in the quality database.

Roles and responsibilities

9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.

10. Team Managers will provide details of quality checks that have been carried out.

11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.

12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.

Which statement applies to the Records section?

Options:
A.

Delete entry 6 because this information should be included in Stage or Team Plans.

B.

Move entry 6 to the Reporting section because the information should be used to report on quality activities.

C.

Delete entry 7 because this should be included in the Configuration Management Strategy.

D.

Delete entry 8 because the results of quality reviews are recorded in the Quality Register.

Questions 14

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work Package only has one week tolerance.

Which 2 actions should the Team Manager take in response to this situation?

Options:
A.

Ask the reviewers to work overtime to prevent the delay.

B.

Ensure that the situation is included in the next Highlight Report.

C.

Raise an issue explaining that tolerances are forecast to be exceeded.

D.

Advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products.

E.

Ensure that the Quality Register is updated with the quality review result.

Questions 15

Scenario

Extract from the Project Product Description (with errors)

Prince2-Practitioner Question 15

Which 2 statements apply to the Acceptance criteria section?

Options:
A.

Amend entry 21 to 'Appearance - 12 photos each showing different members of staff.

B.

Move entry 21 to Composition because the photos are part of the final product.

C.

Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project.

D.

Move entry 23 to Derivation because the Data Protection Act already exists.

E.

Delete entry 24 because this is NOT a suitable acceptance criteria for this project.

Questions 16

During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

Options:
A.

Highlight report

B.

Checkpoint Report

C.

Issue Report

D.

End Stage Report

Questions 17

Column 1 is a list of entries from the Daily Log that occurred during stage 4 in the Controlling a Stage process. For each entry in Column 1, select the first management product from Column 2 that should have been updated, or created, as a result of the entry. Each selection from Column 2 can be used once, more than once or not at all.

Drop down the right answer from column 1 to column 2.

Prince2-Practitioner Question 17

Options:
Questions 18

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?

Options:
A.

Benefits Review Plan

B.

End Project Report

C.

Follow-on action recommendations

D.

Project closure notification

Questions 19

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

Options:
A.

Issue Register

B.

Follow-on action recommendations

C.

Lessons Report

D.

Risk Register

Questions 20

Which of the following statements is FALSE regarding the Continued Business Justification?

Options:
A.

The justification for the project must remain the same throughout the project

B.

The justification for the project should remain valid

C.

The justification for the project may change

D.

If the project is no longer justified it should be stopped