Free PRINCE2 Prince2-Foundation Practice Exam with Questions & Answers | Set: 5

Questions 41

Which is a purpose of an End Project Report?

Options:
A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

PRINCE2 Prince2-Foundation Premium Access
Questions 42

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Options:
A.

Off-specifications

B.

Follow-on action recommendations

C.

Issue Register

D.

Risk Register

Questions 43

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Options:
A.

Directing a Project

B.

Controlling a Stage

C.

Managing a Stage Boundary

D.

Managing Product Delivery

Questions 44

Which is a purpose of the Controlling a Stage process?

Options:
A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

Questions 45

Which is NOT a purpose of the Organization theme?

Options:
A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Questions 46

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Options:
A.

Create a separate Project Board to manage the supplier elements of the project

B.

Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.

C.

Create user and supplier groups

D.

Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board

Questions 47

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:
A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Questions 48

Whose approval is needed to replace a Stage Plan with an Exception Plan?

Options:
A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Questions 49

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

Options:
A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

Questions 50

Which is one of the three levels of plan in PRINCE2?

Options:
A.

Benefits Review Plan

B.

Programme Plan

C.

Team Plan

D.

Project Brief