Free PRINCE2 Prince2-Foundation Practice Exam with Questions & Answers | Set: 12

Questions 111

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the ‘business case' practice when the project board undertakes this review?

Options:
A.

Manage by exception

B.

Manage by stages

C.

Focus on products

D.

Tailor to suit the project

PRINCE2 Prince2-Foundation Premium Access
Questions 112

Thea project manager needs to report to the project board on the status of the project's issues.

Which management product should the project manager review?

Options:
A.

Project log

B.

Project brief

C.

Checkpoint report

D.

Highlight report

Questions 113

Which role is responsible for focusing on the safety and well-being of the project team?

Options:
A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Questions 114

The senior user needs to understand how user assurance will support the senior user on the project.

Which management product should the senior user review?

Options:
A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Questions 115

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:
A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Questions 116

What is an advantage of dividing the project into stages?

Options:
A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Questions 117

Which is a benefit of using PRINCE2?

Options:
A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Questions 118

Which is a benefit of applying the ‘tailor to suit the project’ principle?

Options:
A.

Project management becomes less bureaucratic

B.

The capability of leadership is strengthened

C.

The project environment complexity is reduced

D.

The number of outputs is reduced

Questions 119

What statement describes how the project manager should ensure effective communication within a project?

Options:
A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Questions 120

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?

Options:
A.

Project brief

B.

Business case

C.

Benefits management approach

D.

Project plan