Free PRINCE2 Prince2-Foundation Practice Exam with Questions & Answers | Set: 3

Questions 21

Which risk response is applied on a pain/gain basis?

Options:
A.

Share

B.

Accept

C.

Exploit

D.

Enhance

PRINCE2 Prince2-Foundation Premium Access
Questions 22

Who represents the three project interests on a project?

Options:
A.

Project manager

B.

Project support

C.

External project stakeholders

D.

Project board

Questions 23

What must a PRINCE2 project demonstrate?

Options:
A.

Application of PRINCE2 principles

B.

Application of proper leadership skills

C.

Application of the activities in each process

D.

Application of tools appropriate for the industry

Questions 24

What is a supplier of a PRINCE2 project responsible for?

Options:
A.

Providing the project mandate

B.

Providing resources to deliver the project outputs

C.

Establishing the project's governance

D.

Realizing the benefits from the project

Questions 25

Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:
A.

Progress

B.

Change

C.

Organization

D.

Quality

Questions 26

Identify the missing words in the following sentence.

When proposed changes [ ? ], the change authority must refer the decision back to the project board.

Options:
A.

are below the agreed change budget

B.

are objected to by team members

C.

are rejected by the change authority

D.

exceed the agreed change budget

Questions 27

What is performed as part of the recommended risk management procedure?

Options:
A.

A budget to investigate issues is allocated

B.

Risk management practices are reviewed to ensure that they are performed effectively

C.

Information about risks to the projects is sent to project stakeholders

D.

Conflicts between the project and the programme board are resolved

Questions 28

Which describes a characteristic of a project?

Options:
A.

It maintains business as usual profitability

B.

It provides a quality service to customers

C.

It involves a team with different skills

D.

It enables established and proven best practices

Questions 29

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

Options:
A.

Project mandate

B.

Initiation stage plan

C.

Project initiation documentation

D.

Project brief

Questions 30

According to PRINCE2, why might there be more than one business case for a project?

Options:
A.

There may be more than one management stage in the project

B.

The project may be in a commercial environment with a number of suppliers

C.

There may be more than one work package being delivered in the project

D.

The project may be in a programme environment