Questions 11

Which of the following is a process of monitoring the status of the project and product scope?

Options:
A.

Control scope

B.

Perform quality control

C.

Identify risk

D.

Plan quality

GIAC GCPM Premium Access
Questions 12

Which of the following documents refers specifically to the input output mechanism that serves the purpose of providing a narrative description of the sum of the scope of the project?

Options:
A.

Project scope statement

B.

Project WBS

C.

Project WBS dictionary

D.

Project charter

Questions 13

You work as a project manager for PassGuide Inc. You want to include a budget contingency to accommodate the risk of incurring unidentifiable but normally occurring costs within the defined scope. Which of the following processes will help you to accomplish the task?

Options:
A.

Cost baselining

B.

Cost controlling

C.

Cost estimation

D.

Cost budgeting

Questions 14

Which of the following techniques is described in the statement below?

"It is an early warning project management tool that allows managers to discover and control errors before they become unmanageable."

Options:
A.

Resource leveling

B.

Earned Value Analysis

C.

What-if scenario analysis

D.

Variance analysis

Questions 15

Which of the following is a measure of progress achieved compared to progress planned on a project?

Options:
A.

Cost variance

B.

Schedule performance index

C.

Schedule variance

D.

Cost performance index

Questions 16

You are the project manager of TRT project. During execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him.

Which of the following is not a recommended step in order to resolve the issue?

Options:
A.

Apply team building measures to improve the team's effectiveness.

B.

Get more feed back from Rick.

C.

Get feedback on Rick from other team members.

D.

Shift Rick to another project.

Questions 17

Which of the following process groups starts after the planning phase of a project is over?

Options:
A.

Monitoring and Controlling

B.

Initiation

C.

Testing

D.

Execution

Questions 18

Which of the following processes is performed to develop a detailed description of the project and product?

Options:
A.

Initiation

B.

Scope definition

C.

Planning

D.

Scope verification

Questions 19

Which of the following are inputs of the perform quality assurance process?

Each correct answer represents a complete solution. Choose all that apply.

Options:
A.

Project management plan

B.

Change requests

C.

Quality metrics

D.

Work performance information

Questions 20

Which of the following is built by aggregating the costs of the individual work elements and then joining them at time intervals where meaningful actual cost information will be available?

Options:
A.

Cost baseline

B.

Cost estimation

C.

Cost controlling

D.

Cost budgeting

Exam Code: GCPM
Certification Provider: GIAC
Exam Name: GIAC Certified Project Manager Certification Practice Test
Last Update: Sep 12, 2025
Questions: 397

GIAC Free Exams

GIAC Free Exams
Prepare for GIAC certification with free access to reliable study resources and practice tests at Examstrack.