Free Exin CDCP Practice Exam with Questions & Answers | Set: 2

Questions 11

New server equipment is arriving at your data centre, where should it be tested?

Options:
A.

In the Holding area

B.

In the Computer! Server room

C.

In the Media storage area

D.

In the Staging room

Exin CDCP Premium Access
Questions 12

Which one of the following is a core objective of a Business Value in an organization?

Options:
A.

Reducing Costs

B.

Reducing the Deficit

C.

Increasing Sales

D.

None of the above

Questions 13

Mean time between failures is best considered a measure of:

Options:
A.

Size

B.

Cost

C.

Duration

D.

Reliability

Questions 14

What should be considered when implementing hot- or cold-aisle containment in an existing computer room?

Options:
A.

Equipment will get too hot at the rear (back) of the rack potentially resulting in more ICT hardware failures.

B.

The delta-T of the equipment will increase too much causing reliability issues.

C.

It creates potential issues with the existing fire suppression system(s).

D.

It will be more difficult to install power and network cabling in the contained area.

Questions 15

is the arithmetic mean of time between the failing and the subsequent running of the system in a particular time period.

Options:
A.

MTBF

B.

MCBF

C.

MLBF

D.

MTTR

Questions 16

The UPS vendor is offering the latest model of their UPS to you. The vendor indicates that the UPS is categorized as VFD class.

Is this UPS a fit for your mission-critical data centre?

Options:
A.

Yes

B.

No

C.

Yes, but only if you oversize the battery bank with 10%.

D.

Yes, but only if they install it with a 12-pulse rectifier.

Questions 17

Which type of Humidifier suspends quartz lamps over an open pool of water?

Options:
A.

Infrared Humidifiers

B.

Water Canister Humidifier

C.

Steam Canister Humidifier

D.

Ultrasonic Humidifier

Questions 18

Does unplanned downtime of a data centre have an impact on the business results?

Options:
A.

No, because data centres operate independently from the business.

B.

No, unplanned data centre downtime is already financially planned for in the yearly budget planning process.

C.

Yes, data centre downtime can result in business downtime.

D.

Yes, but data centre downtime only impacts the airline industry.

Questions 19

What is the current recommended temperature for ICT equipment as described in the ASHREA TC 9.9 guideline?

Options:
A.

8-18 C (46.4 -64.4 °F)

B.

20-40 °C (68 - 104 °F)

C.

18-27 C (64.4 - 80.6°F)

D.

25-45 °C (77 - 113 °F)

Questions 20

Starting from which Rating does the requirement of Concurrently Maintainability becomes relevant?

Options:
A.

Rated-4

B.

Rated-3

C.

Rated-2

D.

Rated-1