Free Construction Specifications Institute CDT Practice Exam with Questions & Answers | Set: 3

Questions 21

Which of the following elements should be included in Supplementary Conditions?

Options:
A.

Requirements for a schedule of values

B.

Claims and dispute resolution requirements

C.

Equal employment opportunity requirements

D.

Termination of the work by owner or contractor

Construction Specifications Institute CDT Premium Access
Questions 22

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:
A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Questions 23

Within a project budget, which item falls into the category of a hard cost?

Options:
A.

Architect/engineer design fees

B.

Commissioning fees

C.

Project financing

D.

Land acquisition

Questions 24

How do private bidding practices compare or contrast with public bidding practices?

Options:
A.

A private owner may waive any informality in the bidding, except for the performance bond.

B.

Private bids may be opened in private, but the results must be published in a reasonable time.

C.

The laws and regulations for private bidding are the same as for public bidding.

D.

The private owner may award a contract to a responsive and responsible bidder other than the lowest.

Questions 25

Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?

Options:
A.

Mobilization meeting

B.

Preconstruction meeting

C.

Prebid meeting

D.

Coordination meeting

Questions 26

During design, in a design-build delivery method, what is the design-builder responsible for delivering to the owner?

Options:
A.

Submittals

B.

Record documents

C.

Geotechnical reports

D.

Construction documents

Questions 27

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

Options:
A.

Conformed set

B.

Record set

C.

Change order log

D.

Request for information documents

Questions 28

An architect/engineer (A/E) is reviewing a claim from a contractor asking for more money and time on the project. The A/E plans to reject this claim based on documentation supplied by the contractor indicating what reason?

Options:
A.

There was active interference by the owner.

B.

There were conditions beyond the control of the contractor or owner.

C.

The A/E modified the contract documents.

D.

There is defective work needing repair.

Questions 29

In the AIA A201 General Conditions of the Contract for Construction, whom is responsible for property insurance for a project?

Options:
A.

Surety, on contractor's behalf.

B.

Owner, unless assigned to contractor.

C.

Owner and contractor, jointly.

D.

Contractor, unless assigned to owner.

Questions 30

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

Options:
A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase