Free Construction Specifications Institute CDT Practice Exam with Questions & Answers | Set: 2

Questions 11

When do negotiations take the place of bidding?

Options:
A.

When exact quantities of work cannot be determined.

B.

When a publicly funded project's lowest bid exceeds the budget.

C.

When the contractor has defaulted on insurance premiums.

D.

When the owner and contractor have established a level of trust.

Construction Specifications Institute CDT Premium Access
Questions 12

Lump sum, unit price, and cost-plus-fee are examples of what?

Options:
A.

Delivery method

B.

Bonding system

C.

Basis of payment

D.

Cost estimate

Questions 13

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:
A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Questions 14

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:
A.

The construction schedule

B.

The subcontractor’s invoices

C.

The schedule of values

D.

The percentage of completion

Questions 15

Which document directly modifies the requirements of the general conditions?

Options:
A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Questions 16

As a project manager representing a private client, which of the following instances would best benefit from a constructability review meeting?

Options:
A.

The client is unfamiliar with this type of project.

B.

The project team consists of multiple new members.

C.

The site presents unusual challenges and constraints.

D.

The contractor is unable to commit to original schedule.

Questions 17

Peer reviews or internal reviews of completed documents are examples of what?

Options:
A.

Quality control

B.

Commissioning

C.

Quality assurance

D.

Construction administration

Questions 18

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?

Options:
A.

Solicitation

B.

Instructions for Procurement

C.

Instructions to Bidders

D.

Request for Scope of Work

Questions 19

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:
A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Questions 20

When is the owner entitled to stop the work?

Options:
A.

If the architect/engineer fails to represent owner properly

B.

If the contractor fails to correct work that is not compliant with the contract documents

C.

If the contractor is presumed to be bankrupt

D.

If there is a safety problem on the site