Free CIPS L6M5 Practice Exam with Questions & Answers | Set: 2

Questions 11

Below are descriptions of five companies in the UK. Each company has a unique organisational culture and a key Cultural Web Influence that shapes its structure and operations.

Your task is to match the correct type of organisational culture and cultural web influence to each company.

Company Descriptions

    Company 1

      Description: Authority is centred around the founder. There are strict financial systems and a reward/bonus scheme for meeting targets.

Company 2

    Description: Employees operate independently and often bring in their own clients. There is a strong corporate identity and branding.

Company 3

    Description: Strict hierarchy determines salary and job titles. The organisation is described as bureaucratic and follows stringent rules.

Company 4

    Description: Employees work in small teams or individually on projects. There is a strong emphasis on weekly team meetings where tasks for the upcoming week are discussed.

Company 5

    Description: Authority is held by senior leadership who make all decisions. There are few rules, and culture is reinforced by storytelling about past successes.

L6M5 Question 11

Options:
CIPS L6M5 Premium Access
Questions 12

Giant Construction Company is working on five large-scale projects. Each project has a specific contract type and pricing mechanism.

Your task is to match the correct contract type and pricing mechanism to each project.

Project Descriptions

    Project 1

      Description: Giant is collaborating closely with the client to construct a hospital. The client has provided a cost estimate, and any savings will be shared between the parties. This contract is popular in the public sector due to its flexibility.

Project 2

    Description: This suite of contracts is known as the "rainbow suite". It is rigid, meaning no changes can be made after signing. The price was fixed at the date of signing.

Project 3

    Description: This international project involves the construction of wind turbines. The pricing mechanism calculates costs for each individual turbine.

Project 4

    Description: The most popular form of contract in construction, utilizing a Contract Administrator to ensure timely information flow. Since the scope was not clearly defined, Giant is working with the client on a cost-sharing basis plus a small profit margin.

Project 5

    Description: The project involves ICT services and software provision. Payments are linked to milestone completion during the project implementation phase.

L6M5 Question 12

Options:
Exam Code: L6M5
Certification Provider: CIPS
Exam Name: Strategic Programme Leadership
Last Update: Jul 15, 2025
Questions: 83
PDF + Testing Engine
$164.99
$66
Testing Engine
$124.99
$50
PDF (Q&A)
$104.99
$42