Questions 31

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?

Options:
A.

Continuous compounding rate

B.

Simple interest rate

C.

Minimum attractive rate of return

D.

Nominal interest rate

AACE International CCP Premium Access
Questions 32

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of SO 45 cents is estimated.

The monthly fixed costs are: Rant-$1,600

Wages - S4.000

Miscellaneous fixed expenses - $500

If the rent increases by 100% and the unit sales/other costs remain unchanged, the new break even amount is?

Options:
A.

$33,750

B.

$375,00

C.

$7,500

Questions 33

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

You are reporting on a roadway project, which was estimated to be 10 miles of road. It was scheduled to be completed in 16 weeks, which is this week. According to your calculations, the project has aschedule performance index of 0.80. What would you advise the management about the scheduled completion date?

Options:
A.

Project will be completed in 20 more weeks

B.

Project will be completed this week - on schedule

C.

Project will be completed in 4 more weeks

D.

Project will be completed in 12.8 more weeks

Questions 34

A project's data shows the budgeted cost of work scheduled as $27,000 and the actual cost of work performed as $25,000. If the baseline budget is $200,000 and the work o-ogress is 12%. what is the cost performance index (CPI)?

Options:
A.

1

B.

1.04

C.

0.89

D.

0.96

Questions 35

When a person hears the words being said to him/her, but does not receive the message of the words, it is called

Options:
A.

Reflective listening

B.

Judgmental listening

C.

Passive listening

D.

Directive listening

Questions 36

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the "book value (BV) of the asset at the end of 5 years?

Options:
A.

$64,000

B.

$16,000

C.

$3,200

D.

$60,000

Questions 37

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

Options:
A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

Questions 38

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

According to Maslow's hierarchy of needs, giving the employees an award that acknowledges their achievements is most likely to satisfy which level of need?

Options:
A.

Belonging needs

B.

Safety needs

C.

Power needs

D.

Self-actualization

Questions 39

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow’s hierarchy of needs?

Options:
A.

Belonging needs

B.

Self-actualization

C.

Knowledge

D.

Pay and compensation

Questions 40

In the application of the benefit/cost method of analysis, what are the criteria for determining whether a proposed project is acceptable?

Options:
A.

B/C is - 1.0

B.

B/C is <1.0

C.

B/C is > minimum ROR

D.

B/C is >1.0

Exam Code: CCP
Certification Provider: AACE International
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Jul 17, 2025
Questions: 189

AACE International Free Exams

AACE International Free Exams
Unlock free AACE International exam resources and practice tests at Examstrack. Boost your AACE International exam readiness with top-notch materials.