Free AACE International CCP Practice Exam with Questions & Answers | Set: 3

Questions 21

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

All of the following are included in "income tax" calculations except:

Options:
A.

Annual income

B.

Annual expenditures

C.

Depreciation

D.

Initial cost of investment

AACE International CCP Premium Access
Questions 22

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Taxes due at the end of year five (5) would be:

Options:
A.

$34,034

B.

$4,912

C.

$11,912

D.

$35,000

Questions 23

Some of the principles of good communication are:

Options:
A.

Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message

B.

Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda

C.

Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated

D.

The social process by which people in a specific situation construct meaning using symbolic behavior

Questions 24

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The compound interest factor used to determine Present Value in year number 5 is:

Options:
A.

0.3790

B.

0.6209

C.

1.6051

D.

0.6830

Questions 25

The process of stating goals and determining the most effective way of reaching them is the definition for:

Options:
A.

Implementing

B.

Mission Statement

C.

Managing

D.

Planning

Questions 26

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the method to estimate the cost of the new rides:

Options:
A.

Break down the technology into components

B.

Call vendors for quotes

C.

Use historical data from past projects

D.

Adjust known data from existing rides

Questions 27

You are analyzing historic unit costs for 18'' Class 5 reinforced concrete pipe is a database. The unit costs include all costs-material, labor, equipment, and other, for the excavation, bedding, pipe and backfill. Refer to the following table:

CCP Question 27

What is the median unit cost?

Options:
A.

$48.22

B.

$48.35

C.

$40.00

D.

$46.59

Questions 28

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Five years from now it is required the company have $100,000. How much money should be invested at the end of each year to reach this?

Options:
A.

$15,937

B.

$15,397

C.

$16,380

D.

$13,168

Questions 29

CCP Question 29

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours have been earned?

Options:
A.

9,979

B.

10,586

C.

11,052

D.

9,559

Questions 30

In a fixed price contract the:

Options:
A.

Contractor has no risk in the project

B.

Contactor assumes all the performance risk

C.

Contractor is paid for actual costs

D.

Owner has all the risk

Exam Code: CCP
Certification Provider: AACE International
Exam Name: Certified Cost Professional (CCP) Exam