You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:

unable to be calculated from the information given

Options:
A.

<1

B.

=1

C.

=1

D.

>1

AACE International CCP Premium Access
Questions 12

CCP Question 12

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?

Options:
A.

6,600

B.

6,960

C.

7,200

D.

6,573

Questions 13

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following calculations would not be needed to determine "net income?'

Options:
A.

Depreciation

B.

Taxes

C.

Present value

D.

Income before taxes

Questions 14

When using a fixed-price./lump-sum contract, which of the following; situations can a payment be made for the adjustment of fluctuations in the cost of of construction resources?

Options:
A.

For changes in prices calculated in accordance with a methodology proposed by the contractor at tender stage.

B.

For changes in construction cost 'or varied works carried out beyond the original dale of completion

C.

In no situation

D.

For changes in The cost of resources beyond the control of either party

Questions 15

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

Options:
A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Questions 16

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

Options:
A.

To be exactly the percentages stated

B.

To fall within the percentage range stated

C.

To be higher or lower that the percentages stated

D.

To be outside the percentages stated

Questions 17

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Which statement best describes the type of information available for a design phase estimate?

Options:
A.

Home office detail, specific vendor quotes, preliminary quantities with labor and material factors applied

B.

Square footage of buildings, factored indirects, types of rides and exhibits identified, utility requirements, conceptual layouts

C.

Detailed construction drawings, quantity takeoffs, detailed labor hours and material costs applied, quotes from all major subcontractors

D.

Utility requirements, detailed building plans and (- specifications, types of rides and exhibits identified, all vendor quotes or estimates received from subcontractors

Questions 18

CCP Question 18

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, the final price for the piece of equipment will be:

Options:
A.

$328,810

B.

$370,710

C.

$375,658

D.

$378,750

Questions 19

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

You have been asked to provide ETC information to management. Based on the following information, what is the ETC?

Original Budget = $9,000,000

Actuals to date = $3,513,000

Current estimate at completion = $10,613,000

Actuals for current month = $1,200,000

Options:
A.

$10,613,000

B.

$9,000,000

C.

$5,487,000

D.

$7,100,000

Questions 20

CCP Question 20

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

An unbalanced bid methodology can best be used by:

Options:
A.

Engineer/contractor working for the owner (Plan B)

B.

Subcontractor working for contractor (Plan A or B)

C.

Contractor working directly for engineer (plan A or B)

D.

Engineer working for the owner (Plan A)

Exam Code: CCP
Certification Provider: AACE International
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Jul 19, 2025
Questions: 189

AACE International Free Exams

AACE International Free Exams
Unlock free AACE International exam resources and practice tests at Examstrack. Boost your AACE International exam readiness with top-notch materials.