Free The Open Group OG0-021 Practice Exam with Questions & Answers | Set: 2

Questions 11

Which of the following answers contains only concepts within the scope of the ArchiMate Implementation and Migration extension?

Options:
A.

Work Package, Artifact, Plateau, Driver

B.

Work Package, Deliverable, Plateau, Gap

C.

Project, Work Package, Deliverable, Plateau

D.

Project, Resource, Deliverable, Gap

Questions 12

The PRO-FIT division of ArchiSurance has a new offering that is described by the following diagram:

OG0-021 Question 12

Which of the following statements most accurately interprets this diagram?

Options:
A.

RepairMaster is a business product that includes three services and is used by three different roles

B.

RepairMaster is a business service that includes three products and is used by three different business actors

C.

RepairMaster is a business object that holds information about three different services, and is accessed by three different roles

D.

RepairMaster is a business product that delivers three different kinds of value to the three different roles that use it

Questions 13

Consider the following diagram:

OG0-021 Question 13

What is the strongest structural relationship that can be derived from business role Actuary to business interaction Close contract (indicated by number 1 in the diagram)?

Options:
A.

Assignment

B.

Aggregation

C.

Realization

D.

Used by

Questions 14

Which application layer concept is defined as a passive element?

Options:
A.

Application component

B.

Application function r

C.

Data object

D.

Business object

Questions 15

Consider the following diagram with four relationships modeled:

OG0-021 Question 15

Which relationship modeled in the diagram is not allowed to connect the application layer with the technology layer?

Options:
A.

Relationship 1

B.

Relationship 2

C.

Relationship 3

D.

Relationship 4

Questions 16

The following diagram shows a typical group of stakeholders:

OG0-021 Question 16

Which ArchiMate viewpoint abstraction level would support these stakeholders for the purpose of change management?

Options:
A.

Coherence

B.

Designing

C.

Details

D.

Overview

Questions 17

Consider the following diagram:

OG0-021 Question 17

What does the diagram express about the relationship between the three processes?

Options:
A.

Take in Claim passes information to Gather Claim Information, and Gather Claim Information passes information to Adjudicate Claim

B.

Take in Claim triggers Gather Claim Information, and Gather Claim Information triggers Adjudicate Claim

C.

Take in Claim is used by Gather Claim Information, and Gather Claim Information is used by Adjudicate Claim

D.

The three processes may execute in parallel, although they don't have to

Questions 18

Which standard ArchiMate viewpoint focuses on the (internal) structure of a company, a department, or a network of companies, and identifies authorities and responsibilities?

Options:
A.

Actor Co-operation viewpoint

B.

Organizational viewpoint

C.

Business Function viewpoint

D.

Business Process Co-operation viewpoint

Questions 19

Consider the following diagram, which represents a migration from a Baseline to a Target Architecture:

OG0-021 Question 19

Which of the following answers best interprets the unlabeled symbol in the middle of the diagram?

Options:
A.

It represents a relatively stable intermediate state during the migration from the Baseline to the Target Architectures

B.

It represents a project that progresses the architecture from Baseline to Target

C.

It represents the deliverables necessary to transform the architecture from Baseline to Target

D.

It represents a conceptual point of transition between the two architectures, but one that is unlikely to exist in reality for more than an instant

Questions 20

The Application Co-operation viewpoint describes the relationships between application components in terms of the information flows between them, or in terms of the services they offer and use.

Which of the following concepts cannot be used in an Application Co-operation view?

Options:
A.

Business object

B.

Location

C.

Application interface

D.

Data object