Free Scrum SAFe-SASM Practice Exam with Questions & Answers

Questions 1

Why is the program predictability measure the primary Metric used during the quantitative measurement part of the Inspect and Adapt event?

Options:
A.

To measure the predictability of business value delivered in the PI timebox

B.

To predict the scope of the remaining requirements in the Program Backlog

C.

To forecast when remaining features could be delivered to customers

D.

To match customer demand to the Agile Release Train's velocity

Scrum SAFe-SASM Premium Access
Questions 2

Which two statements are true about a Feature? (Choose two.)

Options:
A.

It is developed within a single Agile Team

B.

It is fully completed by a single Agile Release Train within one PI

C.

It is prioritized using weighted shortest job first

D.

It has one Capability as a parent

Questions 3

How is team performance calculated in SAFe?

Options:
A.

The ratio of tasks planned to tasks completed

B.

The ratio of business value achieved to business value planned for the PI

C.

The ratio of Story points completed to Story points planned in the PI

D.

Team member utilization as a percentage of total capacity

Questions 4

Which two Framework elements would a Scrum Master have the strongest connection and most frequent interaction? (Choose two.)

Options:
A.

Business Owners

B.

Release Train Engineer

C.

Systems Team

D.

Product Owner

E.

Epic Owner

Questions 5

What is one characteristic of an effective Agile Team?

Options:
A.

To reliably deliver value by deploying features

B.

Uses their manager to define work prioritization

C.

Team members focus on improving their own, specialized skill sets

D.

Has team members who always agree with other's ideas

Questions 6

What are the benefits of organizing teams around Features?

Options:
A.

Teams can avoid decomposing Features into Stones

B.

There are fewer dependencies between teams

C.

It enables specialized skill sets to be used

D.

It eliminates the need for a dependency board

Questions 7

A team consistently receives defect reports from production even though each Story is thoroughly tested. What is the first step to solve this problem?

Options:
A.

Invest in better Story and unit-test automation

B.

Represent a strict definition of done

C.

Ensure that development and testing environments are equivalent to production

D.

Create a story dependency with the systems team to collaborate on deployment

Questions 8

During Iteration planning, the Product Owner introduces multiple new Stories to the team. Following a discussion, the team is unclear on the scope of the work and adds spikes into the Iteration for research. How should a Scrum Master help resolve this issue?

Options:
A.

Have the team work on the Stories and identity the dependencies as they go

B.

Ensure the Product Owner and the team arrived at the planning session with proper preparation

C.

Discourage the team from creating spikes so they can focus on other Stories

D.

Allow the team to finish planning and commit to Stories with existing unknowns

Questions 9

A team integrates and tests the Stories on the last day of the Iteration. This has become a pattern for the last three Iterations. Why is this considered an anti-pattern?

Options:
A.

Because the team is waterfallingthe Iteration

B.

Because the team demonstrates the full Stories to the Product Owner during the Iteration review

C.

Because the team consistently meets their commitments, and the Product Owner accepts the Stories

D.

Because it is difficult to manage dependencies with other teams

Questions 10

Which statement is true about batch size, lead time, and utilization?

Options:
A.

Higher team member utilization leads to longer lead times

B.

There is no direct relationship between lead time and utilization

C.

As batch size increases, lead time decreases

D.

There is no direct relationship between lead time and batch size