New Year Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70track

Free ISTQB ISTQB-CTFL Practice Exam with Questions & Answers | Set: 9

Questions 81

Which of the following is a factor that contributes to a successful review?

Options:
A.

All participants in the review are aware they will be evaluated based on the defects they will find

B.

The author of the work product to be reviewed leads the review meeting.

C.

All participants in the review are trained to deal with the review type and its objectives.

D.

Review metrics must be collected to improve the review process

ISTQB ISTQB-CTFL Premium Access
Questions 82

Confirmation testing is performed after:

Options:
A.

a defect is fixed and after other tests do not find any side-effect introduced in the software as a result of such fix

B.

a failed test, and aims to run that test again to confirm that the same behavior still occurs and thus appears to be reproducible

C.

the execution of an automated regression test suite to confirm the absence of false positives in the test results

D.

a defect is fixed, and if such testing is successful then the regression tests that are relevant for such fix can be executed

Questions 83

Which of the following statements about independent testing is WRONG?

Options:
A.

Independent testing is necessary because developers don't know any testing.

B.

Independent testing is best suited for the system test level.

C.

A certain degree of independence makes the tester more effective at finding defects.

D.

Independent test teams may find other types of detects than developers who are familiar with the system's structure.

Questions 84

Which or the following is a valid collection of equivalence classes for the following problem: An integer field shall contain values from and including 1 to and including 15.

Options:
A.

Less than 0.1 through 14. 15 and more

B.

Less than 1.1 through 14. more than 15

C.

negative numbers. 1 through 15. above 15

D.

Less than 1.1 through 15. more than 15

Questions 85

Which of the following activities does NOT belong to a typical technical review?

Options:
A.

Pre-meeting preparation by reviewers

B.

Using checklists during the meeting

C.

Inviting end-users to the meeting

D.

Preparation of a review report

Questions 86

Which of the following characterizations applies to a test tool used for the analysis of a developer's code prior to its execution?

Options:
A.

Tool support for test design and implementation.

B.

Tool support for static testing.

C.

Tool support for test execution and logging.

D.

Tool support for performance measurement and dynamic analysis.

Questions 87

Which ONE of the following statements BEST applies to checklist-based testing?

Options:
A.

Checklists should contain general guidelines to ensure that all aspects of the software are covered.

B.

Checklists should contain specific test conditions that can be individually and directly checked.

C.

Checklists should primarily consist of automated test cases to maximize efficiency.

D.

Checklists should be used exclusively for functional testing, as they are unsuitable for non-functional testing.

Questions 88

Which of the following CORRECTLY matches the roles and responsibilities in a formal review?

Options:
A.

Facilitator - Fixes defects in the work product under review

B.

Scribe - Collates potential defects found during the individual review activity

C.

Review Leader - Creates the work product under review

D.

Author - Identify potential defects in the work product under review

Questions 89

Which of the following is NOT a typical debugging activity when a failure is triggered by dynamic testing?

Options:
A.

Fixing the cause

B.

Reproducing the failure

C.

Diagnosing the root cause

D.

Adding new test cases

Questions 90

A test manager defined the following test levels in her test plan; Component, System and Acceptance.

Which Software Development lifecycle is the Test Manager most likely following?

Options:
A.

V-Model

B.

Agile

C.

Waterfall

D.

Prototyping