Selection of a supplier takes place during which of the following phases of the project management process?

Options:
A.

Project planning

B.

Project initiation

C.

Project monitoring and control

D.

Project execution

ISM INTE Premium Access
Questions 22

During an inventory review, a supply manager confirms that parts used for the maintenance of equipment sold during the previous year are still being stored in the warehouse. These parts cannot be used on current equipment. Which of the following BEST describes these parts’

Options:
A.

Surplus

B.

Excess

C.

Obsolete

D.

Expired

Questions 23

Which of the following refers to the percentage of order requirements met through stock that is present on the shelf?

Options:
A.

Fill rate

B.

Lead time

C.

Inventory turnover

D.

Buffer stock

Questions 24

In an effort to cut expenses, GHI, Inc. moves responsibility for logistics to the supply management department. Some officers in the firm are skeptical that this move will be beneficial, since most shipping providers use published rates, and there will be little room for cost improvement. Which of the following will be the BEST way for GHTs supply manager to demonstrate that supply management skills can obtain better value in shipping?

Options:
A.

Analyze mode, classification and other factors that affect total cost

B.

Utilize supplier performance metrics to ensure optimum rates

C.

Opt for variable freight rates

D.

Conduct carrier cost auditing to reduce net costs of transportation

Questions 25

A firm is looking to expand to a larger warehouse. Which of the following should be given the GREATEST consideration when determining the new warehouse's environmental impact?

Options:
A.

The building's total carbon footprint

B.

The efficiency of the warehouse's air conditioning unit

C.

The cost of replacing single pane windows

D.

The cost of changing light bulbs to LED lights

Questions 26

A manufacturing firm redesigns its premier product to benefit from material standardization. The change will entail re-tooling costs. The firm conducts a cost benefit analysis on four possible options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations involving different materials:

Option 1Option 2Option 3Option 4

Re-tooling Costs (Year 1)$0$800,000$1,000,000$1,200,000

Material Costs

Year 151,000,000$700,000$650,000$600,000

Year 2$1,100,000$750,000$700,000$650,000

Year 3SI,200,000$800,000$750,000$700,000

Year 451,300,000$850,000$800,000$750,000

Year 551,400,000$900,000$850,000$800,000

Total$6,000,000$4,000,000$3,750,000$3,500,000

Labor Costs

Year 1$1,000,000$700,000$650,000$600,000

Year 2$1,100,000$770,000$715,000S660,000

Year 3$1,210,000$847,000$786,500$726,000

Year 4$1,331,000$931,700$865,150$798,600

Year 5$1,464,100$1,024,870$951,665$878,460

Total$6,105,100$4,273,570$3,968,315$3,663,060

In addition to this, there will be a cost of $3.5 million in lost production during Year 1, should any of the re-tooling options (2, 3, or 4) be selected.

The firm wants to rank the options in order of financial preference, from the best option to the worst. Based on this information, how should the four options be ranked?

Options:
A.

2, 3, 1, 4

B.

4, 1, 3, 2

C.

4, 3, 2, 1

D.

1, 2, 3, 4

Questions 27

A firm wants to contract with two suppliers to develop a cellphone tower servicing five million customers. The new technology is required within the next 36 months and has a large budget. The following suppliers are under consideration:

•Supplier A - Has been in business for 20 years; however, every two to three years, its labor force goes on strike

•Supplier B - An established business located in an overseas country which may charge an additional 2% duty on some imported goods

•Supplier C - An established business which has been closed on recent occasions by governing authorities due to health and safety violations

•Supplier D - Has the smallest facilities and workforce of the four, but will be expanding over the next three months and has successfully subcontracted work in order to meet timelines

Based on this information, which two suppliers offer the BEST capacity and capability?

Options:
A.

Suppliers B and D

B.

Suppliers C and D

C.

Suppliers A and C

D.

Suppliers A and B

Questions 28

When an organization is devising a long-term forecast, consulting external sources of information is MOST useful

Options:
A.

for setting realistic organizational goals

B.

in gathering market intelligence

C.

in eliminating irrelevant data

D.

for benchmarking a specific competitor

Questions 29

A cell phone retailer experiences excess inventory of a particular model due to errors in demand forecasting. In addition, remorse returns of this model are greater than anticipated. Which of the following is the BEST course of action the company can take to recover value from these assets?

Options:
A.

Execute an online auction in the secondary market to resell the new devices and the remorse returns

B.

Deploy a permanent e-commerce platform for the sale of the assets, as this will be useful for any future instances of excess and remorse return

C.

Contract with a third-party specialist for the destruction of the returned assets and the resale of the raw materials that result

D.

Use an e-commerce provider for the sale of the device using a revenue share and risk compliance model

Questions 30

A company determines that demand for an item is steady at 800 units per month, and that the cost of ordering and receiving the item is $300, regardless of how much is ordered. The per item charge is $5, and holding costs are 20% annually. Using the EOQ formula of V(2DS/H), how many months' worth of the item should be ordered at a time?

Options:
A.

2

B.

4

C.

3

D.

1

Exam Code: INTE
Certification Provider: ISM
Exam Name: Supply Management Integration
Last Update: Jul 10, 2025
Questions: 167

ISM Related Exams

How to pass ISM CORE - Supply Management Core Exam Exam
How to pass ISM LEAD - Leadership and Transformation in Supply Management Exam

ISM Free Exams

ISM Free Exams
Examstrack offers free ISM exam materials and practice tests to aid your ISM certification journey.