Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70track

Free FIDIC CCM Practice Exam with Questions & Answers | Set: 3

Questions 21

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor ' s reporting requirement end?

Options:
A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

FIDIC CCM Premium Access
Questions 22

(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:
A.

The Employer shall give a Notice to the Engineer, describing the event or circumstance giving rise to the cost, loss, delay or extension of the Defects Notification Period for which the Claim is made.

B.

The Notice shall be given to the Engineer, as soon as practicable, and no later than 28 days after the claiming Party became aware, or should have become aware, of the event or circumstance.

C.

A Notice from the Employer is not required in order to give a Notice to the Engineer for services requested by the Contractor.

D.

The Notice given by the Employer must also include the legal or contractual basis of the claim, including the clause of the Contract under which it is made.

Questions 23

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

Options:
A.

Yes

B.

No

Questions 24

(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))

Options:
A.

If no notified Commencement Date were more than 8 weeks since the Contract became legally effective, the Contractor will be entitled to financial compensation.

B.

The Employer’s failure to notify the Commencement Date within 6 weeks after the date on which the Contract comes into full force and effect would constitute a breach of the Contract.

C.

If no notified Commencement Date were more than 8 weeks since the Contract was legally effective, the Contractor will be entitled to extension of time.

D.

The Contractor shall be entitled to give notice of termination if the Contractor does not receive a Notice of Commencement Date within 12 weeks after both Parties signed the Contract Agreement.

Questions 25

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:
A.

True

B.

False

Questions 26

(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))

Options:
A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

Questions 27

(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))

Options:
A.

Yes, but Contractor will do so on its own risk.

B.

Yes, Contractor can start design and execution of the Works to make sure it won ' t lose any time.

C.

No, because any design or execution before the Commencement Date is prohibited in Clause 8.

D.

Yes, but Contractor will do so on Employer ' s risk.

Questions 28

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back-to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:

" Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer ' s Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer ' s Requirements, its items of reference or Contractor ' s design of the Works for the scope part for which Subcontractor is contracted. "

What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?

Options:
A.

I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.

B.

I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.

C.

I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer ' s Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even

D.

I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer ' s Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to

Questions 29

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:
A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Questions 30

You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?

Choose all of the correct answers (multiple possibilities).

Options:
A.

Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.

B.

Specify Commencement Date in the Contract Agreement.

C.

Specify Commencement Date in the Particular Conditions.

D.

Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.

Exam Code: CCM
Certification Provider: FIDIC
Exam Name: Certified Contract Manager
Last Update: Apr 7, 2026
Questions: 140

FIDIC Free Exams

FIDIC Free Exams