Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free FIDIC CCM Practice Exam with Questions & Answers | Set: 3

Questions 21

Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?

Options:
A.

"The Employer obtains the best value for money" AND "Disputes should be avoided to the extent achievable."

B.

"Only the Employer should be the one to obtain the best value for money" AND "The Contractor/Subcontractor is paid adequately and timely in accordance with the Contract to maintain its cash flow."

C.

"The Contractor/Subcontractor is paid adequately and in a timely manner in accordance with the Contract to maintain its cash flow" AND "The terms of the Contract are comprehensive and fair to primarily the Employer".

D.

"The Contractor should take advantage of its bargaining power every time possible" AND "Disputes are avoided to the extent achievable, minimised when they do arise, and resolved efficiently."

FIDIC CCM Premium Access
Questions 22

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

Options:
A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

Questions 23

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?

Options:
A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Questions 24

Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).

Options:
A.

The Contractor is required to proceed in accordance with the Programme and the Employer's Personnel shall be entitled to rely upon the Programme in planning their activities.

B.

Nothing in any Programme will relieve the Contractor from any obligations to give contractual notice under the Conditions of Contract.

C.

The Programme is a contract document, and thus, considered binding on the Parties.

D.

The Engineer/Employer is not required to review the Programme, and also not required to inform the Contractor if the Programme does not comply with the Contract.

Questions 25

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

Options:
A.

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.

The Contractor cannot terminate the Contract.

C.

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

Questions 26

If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:
A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer's determination and not the Engineer's determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer's necessary approval.

Questions 27

Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:
A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

Questions 28

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:
A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.

B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.

C.

Yes, because otherwise the Contractor doesn't have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.

D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor's Documents in the Employer's Requirements, as stated in Sub-Clause 5.2.

Questions 29

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements areNOTapplicable reasons?

(Choose all correct answers — multiple possibilities)

Options:
A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor's Personnel.

D.

Increase the performance of the Works when completed.

Questions 30

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Options:
A.

True

B.

False

Exam Code: CCM
Certification Provider: FIDIC
Exam Name: Certified Contract Manager
Last Update: Sep 12, 2025
Questions: 100
PDF + Testing Engine
$164.99
$66
Testing Engine
$124.99
$50
PDF (Q&A)
$104.99
$42

FIDIC Free Exams

FIDIC Free Exams