Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 70track

Free FIDIC CCM Practice Exam with Questions & Answers

Questions 1

A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.

Options:
A.

The Employer should check on the Appendix to Tender, Employer ' s Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.

B.

If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub-Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.

C.

Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.

D.

As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.

FIDIC CCM Premium Access
Questions 2

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

Options:
A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.

C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor ' s items on the Site.

D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor ' s items on the Site if the Contractor fails, as this is the Contractor ' s obligation.

Questions 3

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

Options:
A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor ' s Representative or Employer ' s Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

Questions 4

(Please select the one answer in which the mentioned documents are in the correct order (hierarchy), as mentioned in the standard Contract Agreement form of the FIDIC Silver Book (edition 1999).)

Options:
A.

Contract Agreement, Conditions of Contract, Employer’s Requirements, Contractor ' s Tender, Addenda.

B.

Contract Agreement, Conditions of Contract, Addenda, Contractor ' s Tender, Employer’s Requirements.

C.

Contract Agreement, Conditions of Contract, Addenda, Employer’s Requirements, Contractor ' s Tender.

D.

Contract Agreement, Addenda, Conditions of Contract, Employer’s Requirements, Contractor ' s Tender.

Questions 5

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

Options:
A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.

B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.

C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.

D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.

Questions 6

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)

Options:
A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.

B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.

C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.

D.

Both ' Disagreement ' and ' Dispute ' are defined terms under the Conditions of Contract.

Questions 7

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:
A.

The Contractor failed to renew the Tender Security.

B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.

C.

The Employer had submitted a claim under Sub-Clause 20.2.

D.

The Engineer had issued instruction to replace part of the Works.

E.

The Contractor failed to extend the validity of the Performance Security.

Questions 8

Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:
A.

The Contractor is responsible for the performance of the Nominated Subcontractors

B.

Deletion of Sub-Clauses 20.2 - 20.4 for a Project constructed in United Arab Emirates

C.

The DAB Decision is final and binding

D.

The Payment shall be released by the Employer within 180 days calculated from receiving the Contractor ' s Monthly Statement

Questions 9

Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:
A.

The Engineer shall receive a copy of the evidence(s) demonstrating Contractor ' s payment of the necessary insurance premiums.

B.

The Engineer is entitled to take out an insurance on behalf of the Contractor, in case the Contractor fails to extend the validity of a specific insurance.

C.

The Engineer should continuously monitor that the Contractor ' s insurance policies are kept valid, and extensions are duly arranged, when necessary.

D.

The Engineer shall immediately suspend all construction activities at the Site, in case the Contractor failed to take out any necessary insurance.

Questions 10

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

Options:
A.

True

B.

False

Exam Code: CCM
Certification Provider: FIDIC
Exam Name: Certified Contract Manager
Last Update: Apr 7, 2026
Questions: 140

FIDIC Free Exams

FIDIC Free Exams