Free ASQ CCQM Practice Exam with Questions & Answers | Set: 2

Questions 11

Which of the following is the best benefit of aligning the project quality plan with other management plans?

Options:
A.

It integrates the quality plan into organizational objectives.

B.

It identifies any conflicts between the quality plan and financial objectives.

C.

It promotes buy-in from the project team when adopting the quality plan.

D.

It demonstrates why the quality plan should take precedence over other plans.

ASQ CCQM Premium Access
Questions 12

When evaluating the warranty program documentation during project turnover, it is crucial to verify that

Options:
A.

the warranty documentation is included in the project's final financial report

B.

the warranty information was reviewed during the last project audit

C.

the documentation provides clear instructions on filing claims and whom to contact for warranty issues

D.

all project managers have signed off on the warranty documents

Questions 13

The main reason for incorporating recognized sustainability accreditations into projects is to

Options:
A.

decrease the initial project cost through sustainability credits

B.

accelerate project completion by meeting green standards earlier

C.

reduce the length of project audits because of these certifications

D.

increase efficiency and improve long-term project viability

Questions 14

What is the most effective way to evaluate areas for improvement identified by CoQ data analysis?

Options:
A.

Focus improvements on the highest cost and impact areas

B.

Prioritize improvements based on ease and speed of implementation

C.

Assess the root causes of high CoQ areas and determine if improvements align with strategic objectives

D.

Implement random sampling techniques to choose areas for improvement

Questions 15

A construction company is experiencing a significant increase in material waste on multiple sites. Which of the following quality tools should be used to identify and prioritize the biggest sources of waste?

Options:
A.

Use a scatter diagram to analyze the relationship between material suppliers and waste levels.

B.

Utilize flowcharts to map out the entire material procurement process.

C.

Apply a Pareto chart to identify and prioritize the biggest sources of waste.

D.

Implement control charts to monitor waste levels over time.

Questions 16

Which of the following is the most effective way for a construction quality manager to review an 'action' submittal to ensure alignment with the project's quality plan?

Options:
A.

Approve the submittal based on cost-effectiveness.

B.

Prioritize speed of approval to keep the project on schedule.

C.

Verify the submittal meets all specified standards and requirements.

D.

Involve subcontractors in the review process with regular oversight.

Questions 17

Which of the following negative outcomes is most likely to occur when quality resources are demobilized prematurely at the end of a construction project?

Options:
A.

Increased need for interim management

B.

Immediate reduction in operational costs

C.

Potential delay in project deliverables

D.

Increased risk of non-conformance issues

Questions 18

What is the primary purpose of conducting an internal audit in an organization?

Options:
A.

To prepare for potential external legal scrutiny

B.

To assess compliance with a company's policies and procedures

C.

To evaluate the performance of external suppliers

D.

To monitor competitor activities

Questions 19

How should periodic reports be evaluated to ensure they effectively identify quality trends and support waste elimination efforts in a construction project?

Options:
A.

By assessing whether the reports are consistently referenced during decision-making meetings to justify strategy changes

B.

By focusing on the number of reports generated each month to ensure continuous monitoring

C.

By verifying whether the reports are easily accessible to the project team and external auditors

D.

By determining whether reports identify areas of waste and inefficiency that can be targeted for improvement

Questions 20

What is the most effective way for a Construction Quality Manager to monitor the quality impacts of shutdowns?

Options:
A.

By documenting the financial costs associated with shutdowns

B.

By analyzing how shutdowns impact both short-term progress and long-term project quality

C.

By prioritizing monitoring efforts on planned shutdowns that involve critical systems

D.

By focusing on quality issues that could cause significant delays or rework

Exam Code: CCQM
Certification Provider: ASQ
Exam Name: Certified Construction Quality Manager
Last Update: Jul 10, 2025
Questions: 165

ASQ Related Exams

How to pass ASQ CQE - Certified Quality Engineer Exam Exam
How to pass ASQ CMQ-OE - Certified Manager of Quality/Organizational Excellence Exam Exam
How to pass ASQ CSQE - Certified Software Quality EngineerExam Exam

ASQ Free Exams

ASQ Free Exams
Boost your ASQ exam readiness with free materials and practice tests from Examstrack. Get started today at Examstrack.