Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free Scrum PSPO-I Practice Exam with Questions & Answers | Set: 4

Questions 31

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog for a Sprint to satisfy the stakeholders.

Options:
A.

True

B.

False

Scrum PSPO-I Premium Access
Questions 32

When should a Sprint Goal be created?

(choose the best answer)

Options:
A.

A Sprint Goal is not mandatory in Scrum.

B.

It should have been created in the previous Sprint during Product Backlog

refinement.

C.

It must be established before Sprint Planning in order to begin planning.

D.

During Sprint Planning.

E.

At any time during the Sprint.

Questions 33

Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency?

(choose the best answer)

Options:
A.

The Product Backlog is only updated at the Sprint Review, when both the Scrum

Team and the stakeholders are available.

B.

Product Backlog items should hold no more than 8 points of work, which is the

average in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.

C.

Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.

D.

The Product Backlog is only updated at a release planning meeting with the

stakeholders and the change control board present.

E.

The Product Backlog is continually kept up to date with the most recent insights.

Questions 34

True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

Options:
A.

True

B.

False

Questions 35

Who is on the Scrum Team?

(choose all that apply)

Options:
A.

Scrum Master.

B.

Product Owner.

C.

Developers.

D.

Project Manager.

E.

None of the above.

Questions 36

Who determines how many Product Backlog items the Developers select for a Sprint?

(choose the best answer)

Options:
A.

The Scrum Team

B.

The Developers.

C.

The Product Owner.

D.

The Scrum Master.

E.

The stakeholders attending Sprint Planning.

Questions 37

Which of the following is an example of an Increment?

(choose the best answer)

Options:
A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of product features.

F.

All of the above.

Questions 38

How much time is required after a Sprint to prepare for the next Sprint?

(choose the best answer)

Options:
A.

The break between Sprints is timeboxed to one-week for a one-month Sprint, and

usually less for shorter Sprints.

B.

Enough time for the requirements for the next Sprint to be determined and

documented.

C.

Enough time for the Developers to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

Questions 39

What does it mean to say that an event has a timebox?

(choose the best answer)

Options:
A.

The event can take no more than a maximum amount of time.

B.

The event must take at least a minimum amount of time.

C.

The event must happen by a given time.

D.

The event must happen at a set time.

Questions 40

True or False: Multiple Scrum Teams working on the same product must have the same Sprint

start date.

Options:
A.

True

B.

False