Free Scrum PSK-I Practice Exam with Questions & Answers

Questions 1

Which of the following are lagging indicator metrics?

(choose the best three answers)

Options:
A.

Velocity.

B.

Cycle Time.

C.

Work in Progress.

D.

Throughput.

E.

Work Item Aging.

Scrum PSK-I Premium Access
Questions 2

As input for Daily Scrum, which metrics are likely to provide the most actionable data?

(choose the best answer)

Options:
A.

Leading indicators.

B.

Lagging indicators.

Questions 3

What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?

Options:
A.

The team promises to have 85% of all Product Backlog items done within 5 days.

B.

The team can get any critical system backup within 5 days.

C.

The team expects they will complete a work item within 5 days of when they start working on it 85% of the time.

D.

In the last Sprint, the team has been able to complete 85% of Product Backlog items within 5 days of starting work on the item.

Questions 4

Which of these statements are true about Kanban and the Scrum theory of empiricism?

(choose the best two answers)

Options:
A.

The Kanban board provides Scrum Teams with transparency that helps them

inspect and adapt their process.

B.

Kanban metrics are used in the Sprint Review to allow the Product Owner to

inspect the Throughput and adapt the Scrum Team's Cycle Time.

C.

Kanban helps Scrum Teams deal with simple and complicated work where

empiricism is not necessary.

D.

Kanban helps Scrum Teams achieve faster, healthier flow. That brings more

rapid transparency about the product, enabling a more effective inspection and

adaptation loop.

Questions 5

The Cycle Time metric for a certain Work Item cannot be used:

(choose the best two answers)

Options:
A.

As a leading indicator to the length of the feedback loop for that Work Item.

B.

To help the Scrum Team inspect and adapt their process.

C.

As a lagging indicator to the length of the feedback loop for that Work Item.

D.

To help the Developers inspect and adapt their Sprint in the Daily Scrum.

E.

To influence the team's SLE.

Questions 6

A Scrum Team's service level expectation (SLE) is an input into the various Scrum events. In

which event will SLE provide the most benefit towards maintaining good flow?

(choose the best answer)

Options:
A.

Sprint Review.

B.

Sprint Planning.

C.

Sprint Retrospective.

D.

Daily Scrum.

Questions 7

True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. They can instead create one “on-demand” as new work flows into the Sprint Backlog.

Options:
A.

True

B.

False

Questions 8

A Service Level Expectation (SLE) consists of which two items?

(Choose the best two answers)

Options:
A.

A period of elapsed days.

B.

A cost of delay.

C.

A probability.

D.

A forecasted date.

Questions 9

When the Developers limit Work in Progress (WIP) inside a Sprint, what would you expect to observe?

(Choose the best three answers)

Options:
A.

The Developers would stop beginning work, and instead, start finishing work.

B.

The amount of work done by the end of the Sprint would be reduced.

C.

Increased collaboration/swarming between the Developers.

D.

Self-management would be strengthened as a result of increased transparency.

Questions 10

When can a Work in Progress (WIP) Limit change?

(choose the best answer)

Options:
A.

At any time.

B.

When the Product Owner decides to change it.

C.

It never changes.

D.

Only during the Sprint Retrospective.

E.

Only during Sprint Planning.

F.

Only during the Daily Scrum.