Free PRMIA 8010 Practice Exam with Questions & Answers | Set: 6

Questions 51

Which of the following data sources are expected to influence operational risk capital under the AMA:

I. Internal Loss Data (ILD)

II. External Loss Data (ELD)

III. Scenario Data (SD)

IV. Business Environment and Internal Control Factors (BEICF)

Options:
A.

I and II

B.

I, II and III only

C.

III only

D.

All of the above

PRMIA 8010 Premium Access
Questions 52

A corporate bond maturing in 1 year yields 8.5% per year,while a similar treasury bond yields 4%. What is the probability of default for the corporate bond assuming the recovery rate is zero?

Options:
A.

4.15%

B.

4.50%

C.

8.50%

D.

Cannot be determined from the given information

Questions 53

Under the contingent claims approach to credit risk, risk increases when:

I. Volatility of the firm's assets increases

II. Risk free rate increases

III. Maturity of the debt increases

Options:
A.

II and III

B.

I and III

C.

I, II and III

D.

I and II

Questions 54

Which of the following formulae describes CVA (Credit Valuation Adjustment)? All acronyms have their usual meanings (LGD=Loss Given Default, ENE=Expected Negative Exposure, EE=Expected Exposure, PD=Probability of Default, EPE=Expected Positive Exposure, PFE=Potential Future Exposure)

Options:
A.

LGD * ENE * PD

B.

LGD * EPE * PD

C.

LGD * EE * PD

D.

LGD * PFE * PD

Questions 55

Which of the following is not true about the ISDA master agreement (ISDA MA):

Options:
A.

All transactions under the ISDA MA are considered separate obligations

B.

The ISDA MA describes the close out process

C.

The CSA (Credit Support Annex) is one of the parts of the ISDA MA

D.

The ISDA MA describes events of default, and termination events

Questions 56

Which of the following statements are true:

I. Pre-settlement risk is the risk that one of the parties to a contract might default prior to the maturity date or expiry of the contract.

II. Pre-settlement risk can be partly mitigated by providing for early settlement in the agreements between the counterparties.

III. The current exposure from an OTC derivatives contract is equivalent to its current replacement value.

IV. Loan equivalent exposures are calculated even for exposures that are not loans as a practical matter for calculating credit risk exposure.

Options:
A.

II and IV

B.

III and IV

C.

I, II, III and IV

D.

II and III

Questions 57

A long position in a creditsensitive bond can be synthetically replicated using:

Options:
A.

a long position in a treasury bond and a short position in a CDS

B.

a long position in a treasury bond and a long position in a CDS

C.

a short position in a treasury bond and a short position in a CDS

D.

a short position in a treasury bond and a long position in a CDS

Questions 58

Which of the following best describes economic capital?

Options:
A.

Economic capital is the amount of regulatory capital mandated for financial institutions in the OECD countries

B.

Economic capital is the amount of regulatory capital that minimizes the cost ofcapital for firm

C.

Economic capital reflects the amount of capital required to maintain a firm's target credit rating

D.

Economic capital is a form of provision for market risk losses should adverse conditions arise

Questions 59

If E denotes the expected value of a loan portfolio at the end on one year and U the value of the portfolio in the worst case scenario at the 99% confidence level, which of the following expressions correctly describes economic capital requiredin respect of credit risk?

Options:
A.

E - U

B.

U/E

C.

U

D.

E

Questions 60

A key problem with return on equity as a measure of comparative performance is:

Options:
A.

that return on equity is not adjusted for risk

B.

that return on equity are not adjusted for cash flows being different from accounting earnings

C.

that return on equity measures do not account for interest and taxes

D.

that return on equity ignores the effect of leverage on returns to shareholders

Exam Code: 8010
Certification Provider: PRMIA
Exam Name: Operational Risk Manager (ORM) Exam
Last Update: Jul 15, 2025
Questions: 240

PRMIA Related Exams

How to pass PRMIA 8002 - PRM Certification - Exam II: Mathematical Foundations of Risk Measurement Exam
How to pass PRMIA 8004 - PRM Certification - Exam IV: Case Studies; Standards: Governance, Best Practices and Ethics Exam
How to pass PRMIA 8005 - Associate PRM Exam English Exam
How to pass PRMIA 8006 - Exam I: Finance Theory Financial Instruments Financial Markets - 2015 Edition Exam
How to pass PRMIA 8007 - Exam II: Mathematical Foundations of Risk Measurement - 2015 Edition Exam
How to pass PRMIA 8008 - PRM Certification - Exam III: Risk Management Frameworks, Operational Risk, Credit Risk, Counterparty Risk, Market Risk, ALM, FTP - 2015 Edition Exam
How to pass PRMIA 8009 - Exam IV: Case Studies: Standards: Governance, Best Practices and Ethics - 2015 Edition Exam

PRMIA Free Exams

PRMIA Free Exams
Examstrack offers comprehensive free resources and practice tests for PRMIA exams.