A company that wants to add value to its operations should work with its suppliers on which of the following?
DEF, Inc. conducts a Request for Information (RFI) to identify suppliers who will be invited to participate in a Request for Proposal (RFP) for technical support. The RFI requires audited financial statements. DEF receives an inquiry from a publicly traded supplier asking if their 10K statement will suffice, and a privately held supplier states that it will only provide its audited financial statement after receiving a nondisclosure agreement from DEF.
Given this situation, which of the following is the BEST course of action for DEF to take?
A firm is developing a solicitation to purchase materials in order to meet the needs of a new product launch. The firm anticipates that some or all of its existing suppliers will respond to the solicitation. Given this situation, which of the following is the BEST requirements gathering approach for the firm?
A supply manager Is planning for negotiations with a sole-source supplier of an essential part. The buying firm is already one of the supplier's top customers, and will need even larger quantities of the part to expand its product line in the near future. The supply manager learns that the supplier may experience some financial risks over the coming year, and that the supplier is anxious to solidify its relationships with major customers to mitigate that risk. Which of the following Is the BEST way for the supply manager to gain a deeper understanding of the supplier's position?
FGH, Inc. has purchased components from Supplier A for many years. The supplier's performance has been very good, with reliable deliveries and consistently high quality. As contract renewal approaches, Supplier A informs FGH's supply manager that a significant price increase is anticipated, based primarily on the costs of building a new production facility. The supply manager has been directed to negotiate a new contract with Supplier A only if it agrees to maintain current pricing. Which of the following is the BEST way for the supply manager to prepare for negotiations with Supplier A?
A company's accounting department implements a new system to track liabilities for capital assets. The reports developed by this system exclude some important indirect procurement data (e.g., transactions related to test equipment), as this information is tracked by another system. Which of the following is the BEST course of action for the firm to take in this situation?
What is the landed cost per unit for the following item?
Item cost$.76
Packaging for shipment$.02
Shipping from Indonesia$.14
Duty$.03
Customs clearance$.10
Storage at buyer’s warehouse$.09
Shipment from warehouse to plant$.06
XYZ, Inc. is negotiating with Supplier DEF for materials needed in manufacturing. The negotiations are moving slowly, primarily due to delays and postponements by the supplier. DEF has been the primary source for the material under negotiation, and while there are other potential sources, lead times would not make it feasible for XYZ to seek an alternative on such short notice. Which of the following tactics is DEF MOST likely employing?
A supply manager for TUV, Inc. contracts with a new supplier of a critical raw material. After receiving several shipments, TUV's manufacturing team finds too much variation in the material dimensions. A meeting is held between the engineering and quality staffs of both companies to discuss the situation. Which of the following should the supply manager do NEXT?
Which of the following is the FIRST step in the category management process?