Questions 11

Refer to the exhibit.

HPE7-J02 Question 11

Your customer had an unexpected failure of their current storage array, causing them to lose some of their critical data. As a result, they are looking for a storage array with a guarantee of 100% data availability to prevent this failure and loss in the future.

They need 80TB raw and two new 25GbE top-of-rack switches to connect to their environment.

They expect 5% annual growth.

Which correction should be made to the configuration in the exhibit to meet the customer’s requirements?

Options:
A.

Change to 25G networking

B.

Decrease to 20 × 3.84TB drives

C.

HPE GreenLake financial model

D.

Add 2× Aruba 8325 switches

HP HPE7-J02 Premium Access
Questions 12

Review the diagram showing an Active Peer Persistence deployment across two arrays.

HPE7-J02 Question 12

Question: Which Host Proximity Parameter should be configured for ESX31 to ensure localized access?

Options:
A.

Secondary

B.

Primary

C.

Exclusive

D.

All

Questions 13

A customer is replacing their HPE 3PAR 8200 Peer Persistence setup with Alletra 6000. In a recent audit, they were warned that the Quorum Witness VM was missing security updates.

How would you respond regarding the new setup?

Options:
A.

Quorum witness is installed as a service on a supported Linux server, which can be updated as needed.

B.

Quorum witness is deployed as a SaaS option, and security updates are applied automatically.

C.

Quorum witness appliance security patch updates follow the array release train updates.

D.

Quorum witness appliance can be set to automatically download and apply available updates.

Questions 14

Your customer is deploying HPE Morpheus Enterprise Software as a single orchestration platform for compute and storage resources. To achieve a high-availability deployment in a single site, how many VMs must be deployed if distributed databases are not required?

Options:
A.

4 VMs with distributed database setup

B.

1 VM

C.

3 VMs

D.

1 VM with VMware HA and DRS active

Questions 15

Your customer has 2 Alletra 6000 arrays configured for asynchronous replication. The facilities team is planning grid maintenance in the datacenter hosting the source array. They want to proactively move all host I/O to the target array.

Which action needs to be done on the Alletra group level to move the host I/O to the other datacenter?

Options:
A.

Failover

B.

Promote

C.

Demote

D.

Handover