Which aspect of risk assessment is common to all types and levels of RBI?
One of the key elements of an inspection plan is:
The resources and time required to implement an RBI assessment will vary widely between organizations depending on a number of factors including:

The governing inspection codes (such as API 510 and API 570) and jurisdictional regulations, if any, shall be reviewed to determine what?
A risk assessment requires a cost estimate of potential environmental damage. Vessel replacement cost is $116,000, and downtime will be 15 days at a cost of $55,000 per day. The EPA fine for a leak of more than 1500 gallons is $1,650,000, and cleanup will cost $1,145,000. What total value will be assigned to the environmental cost of a leak?
Which mitigation system most effectively minimizes community exposure to a significant release of an acidic water-soluble vapor cloud?
|