Free PMI PMI-SP Practice Exam with Questions & Answers | Set: 10

Questions 91

You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

Options:
A.

$2,975,000

B.

1.02

C.

$139,306

D.

$2,380,000

PMI PMI-SP Premium Access
Questions 92

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below:

MeasurementsValues

BCWP (or EV) 425

BCWS (or PV) 400

ACWP (or AC) 510

What is the schedule performance index (SPI) of the project at the current point of time?

Options:
A.

1.082

B.

0.88

C.

1.0625

D.

0.96

Questions 93

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

Options:
A.

Communications management plan

B.

Issues log

C.

Project schedule

D.

Schedule management plan

Questions 94

You are project manager of HHK project. Examine the network diagram given below:

PMI-SP Question 94

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Options:
A.

Four days

B.

Six days

C.

Five days

D.

Zero, it is on the critical path.

Questions 95

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

Options:
A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Questions 96

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

Options:
A.

Stakeholders are usually identified through a stakeholder register.

B.

Stakeholders are identified by the project team, project sponsor, and management.

C.

Stakeholders are identified through the project customers.

D.

Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.