Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free PMI PMI-SP Practice Exam with Questions & Answers

Questions 1

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

Options:
A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

PMI PMI-SP Premium Access
Questions 2

Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?

Options:
A.

PV/EV

B.

EV-AC

C.

EV-PV

D.

EV/PV

Questions 3

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

Options:
A.

Project calendar

B.

Resource calendar

C.

Organizational calendar

D.

Company calendar

Questions 4

Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?

Options:
A.

Functional manager

B.

Operations manager

C.

Project manager

D.

Seller

Questions 5

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

Options:
A.

Estimate activity durations

B.

Estimate activity resources

C.

Control schedule

D.

Develop schedule

Questions 6

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

Options:
A.

Preventive action

B.

Defect repair validation

C.

Implemented corrective action

D.

Quality control

Questions 7

Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk-adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

Options:
A.

Crashing

B.

Fast tracking

C.

Critical chain methodology

D.

Adding lead time

Questions 8

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

Options:
A.

Diane

B.

Project sponsor

C.

Risk owner

D.

Subject matter expert

Questions 9

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

Options:
A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Questions 10

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

Options:
A.

$142,000

B.

$232,000

C.

$41,750

D.

$23,750

Exam Code: PMI-SP
Certification Provider: PMI
Exam Name: PMI Scheduling Professional
Last Update: Jun 12, 2025
Questions: 323