New Year Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

Free PMI PMI-RMP Practice Exam with Questions & Answers | Set: 4

Questions 31

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:
A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks.

 

PMI PMI-RMP Premium Access
Questions 32

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:
A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Questions 33

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Options:
A.

Being able to monitor and control risks throughout the project.

B.

Defining how risk management will be executed throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Questions 34

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:
A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Questions 35

An organization faces immense competition in the market and decides 10 accelerate a keyproject. What is the first action for the project risk manager to take?

Options:
A.

Ensure sufficient resources are available

B.

Revise the risk management plan

C.

Update the risk register

D.

Meet with the project's stakeholders

Questions 36

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:
A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur.

 

Questions 37

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:
A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

Questions 38

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project's risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:
A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

B.

Log the threats in the risk register to try to minimize the probability of occurrence.

C.

Log the threats in the risk register to try to maximize the probability of occurrence.

D.

Update the project management plan to ensure the results of the opportunities are captured.

Questions 39

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

Options:
A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response.

 

Questions 40

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:
A.

Risk thresholds

B.

Risk response strategies

C.

Risk management reports

D.

Risk breakdown structure (RBS)

Exam Code: PMI-RMP
Certification Provider: PMI
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Mar 28, 2025
Questions: 221