Questions 91

The following chart contains information about the tasks in a project.

PMI-100 Question 91

Based on the chart, what is the cost variance (CV) for Task 6?

Options:
A.

-2,000

B.

0

C.

1,000

D.

2,000

PMI PMI-100 Premium Access
Questions 92

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:
A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Questions 93

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:
A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Questions 94

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:
A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Questions 95

The following is a network diagram for a project.

PMI-100 Question 95

The total float for the project is how many days?

Options:
A.

3

B.

5

C.

7

D.

9

Questions 96

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:
A.

appetite

B.

tolerance

C.

threshold

D.

management

Questions 97

Which items are components of a project management plan?

Options:
A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Questions 98

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:
A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Questions 99

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:
A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Questions 100

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:
A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Questions 101

The chart below is an example of a:

PMI-100 Question 101

Options:
A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Questions 102

Which item is a cost of conformance?

Options:
A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Questions 103

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:
A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Questions 104

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

Options:
A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Questions 105

Analogous cost estimating relies on which of the following techniques?

Options:
A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis