The staffing management plan is part of the:

Options:
A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

PMI PMI-100 Premium Access
Questions 137

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Options:
A.

0.8

B.

0.89

C.

1.13

D.

1.25

Questions 138

The total of the planned value (PV) is also known as:

Options:
A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Questions 139

A tool and technique used during the Collect Requirements process is:

Options:
A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Questions 140

Resource calendars are included in the:

Options:
A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Questions 141

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:
A.

event.

B.

response,

C.

perception.

D.

impact.

Questions 142

Which technique is utilized in the Control Schedule process?

Options:
A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Questions 143

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:
A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Questions 144

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:
A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Questions 145

At the end of the project, what will be the value of SV?

Options:
A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Questions 146

After Define Activities and Sequence Activities, the next process is:

Options:
A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Questions 147

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:
A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Questions 148

The diagram below is an example of a:

PMI-100 Question 148

Options:
A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Questions 149

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:
A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Questions 150

Expected monetary value (EMV) is computed by which equation?

Options:
A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together