Free PMI PMI-002 Practice Exam with Questions & Answers | Set: 5

Questions 61

Which of the following subsidiary plan contains the quality objectives for the project?

Options:
A.

Quality baseline

B.

Quality management plan

C.

Process improvement plan

D.

QA checklist

PMI PMI-002 Premium Access
Questions 62

Which of the following is NOT an input of Estimate Costs?

Options:
A.

Earn Value Analysis

B.

Scope Baseline

C.

P'sk Register

D.

Human Resource Plan

Questions 63

Which of the following statement is true about project charter?

Options:
A.

Provides a high level definition of the effort and its stakeholders

B.

Announces who is the project engineer

C.

Tells the newspapers and media when the project will end

D.

Announces who is the project sponsor

Questions 64

What is the communication channel delta if the members in the communication plan are increased from 5 to 10?

Options:
A.

35

B.

5

C.

15

D.

75

Questions 65

A Risk Register is a part of the ________.

Options:
A.

Project Scope Statement

B.

Project Management plan

C.

Project Scheduling plan

D.

Project Charter

Questions 66

Which of the following is an output of Verify Scope?

Options:
A.

Formal acceptance

B.

WBS template

C.

sow acceptance

D.

Rework

Questions 67

Which statement is true about Bottom-up estimating?

Options:
A.

Estimating the cost of individual work items and then rolling up the costs to arrive at a project total.

B.

Uses the actual cost of a previous similar project as the basis for estimating the cost of the current project.

C.

Using project characteristics (or parameters) in a mathematical model to predict costs.

D.

Cost of quality can also be used to prepare the schedule activity cost estimate.

Questions 68

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:
A.

Parametric estimating

B.

Funding limit reconciliation

C.

Reserves analysis

D.

None of the above

Questions 69

Which of the following project document is best suited for tracking costs of resources?

Options:
A.

Work breakdown structure

B.

P'sk breakdown structure

C.

Organizational breakdown structure

D.

Resource breakdown structure

Questions 70

A requirement document is an input of __________ process?

Options:
A.

Collect Requirements

B.

Define Scope

C.

Integrated Change Control

D.

Monitor and Control Project Work

Questions 71

The intent of the risk management process group is to ________.

Options:
A.

Increase the probability of positive outcomes in the project

B.

Announce project risks

C.

Not consider risks affecting the company

D.

Announce project deliverables

Questions 72

You are the project manager for a Project. Project is a global project. Some peoples are working from US and some are from India. Client says budget should not cost more than $12 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?

Options:
A.

Internationalization

B.

Budget constraint

C.

Management constraint

D.

Quality constraint

Questions 73

Acceptance of the product should be ________.

Options:
A.

Formal

B.

Consistent

C.

Personal

D.

Verbal

Questions 74

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

Options:
A.

Cost plus incentive fee

B.

F'xed P|ice

C.

Time and material

D.

"'s^ 's nc* 'elated to price

Questions 75

Delivery dates and availability of resources can be found in the details of the __________.

Options:
A.

Work Breakdown Structure

B.

sow

C.

Project Charter

D.

Project Scope Statement