Questions 1

Which of the following statements concerning compromise as a conflict resolution is false?

Options:
A.

Neither party wins but both parties get some degree of satisfaction.

B.

Important aspects of the project may be hindered in order to achieve personal objectives.

C.

Compromise is generally considered a lose-lose situation.

D.

A definitive resolution is seldom achieved.

PMI PMI-002 Premium Access
Questions 2

The sender is responsible for ____________.

Options:
A.

Confirming the message is understood

B.

Ensuring the receiver agrees with the message

C.

Scheduling communication exchange

D.

Presenting the message in the most agreeable manner

Questions 3

Which of the following statements is false?

Options:
A.

Uncertainty and risk are greatest at the start of the project and lowest at the end.

B.

The amount at stake Is lowest at the end of the project and greatest at the start.

C.

Expected monetary value can be expressed as the product of the risk event probability and the risk event value.

D.

Opportunities are positive outcomes of risk.

Questions 4

What-if scenario analysis is done as a part of __________ process.

Options:
A.

Sequence Activities

B.

Develop Schedule

C.

Control Schedule

D.

Define Activities

Questions 5

You are a project manager and now you are in the middle of comparing proposals received from sellers. Comparing proposals received from sellers are done in _________.

Options:
A.

Plan Procurements

B.

Conduct Procurements

C.

Administer Procurements

D.

Close Procurements

Questions 6

Management reserves are used to handle which type of risk?

Options:
A.

Unknown unknowns

B.

Known unknowns

C.

Business risks

D.

Pure risks

Questions 7

A series of consecutive points on the same side of the average is called __________.

Options:
A.

Run

B.

Trend

C.

Outliers

D.

Cycle

Questions 8

A key barrier to team development is ______________.

Options:
A.

A strong matrix management structure

B.

Major problems delay the project completion date or budget targets

C.

Team members are accountable to both functional and project managers

D.

Formal training plans cannot be implemented

Questions 9

Most schedule simulations are based on some form of which of the following?

Options:
Questions 10

A schedule activity may start 5 days before the predecessor activity finishes. This is an example of ______________.

Options:
A.

Finish-to-Start

B.

Finish-to-Finish

C.

Start-to-Start

D.

Start-to-Finish

Questions 11

Which of the following is not true about change requests?

Options:
A.

They always require additional funding.

B.

They happen while the project work is being done.

C.

They can be written or verbal.

D.

They can be requested by a stakeholder.

Questions 12

The receiver filters messages based on all but the following:

Options:
A.

Culture

B.

Semantics

C.

Language

D.

Distance

Questions 13

When should the project expeditor form of organization be used?

Options:
A.

The project is extremely important to the organization.

B.

A project's cost and importance are relatively low.

C.

The project manager has a lot of responsibility and accountability.

D.

The organization's primary source of revenue is derived from projects

Questions 14

Which of the following is true about procurement documents?

Options:
A.

Procurement documents are used to solicit proposals from prospective sellers.

B.

Invitations for Bid and Request for Proposal are two examples of procurement documents.

C.

Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.

D.

Al1 of the above

Questions 15

A document or tool which describes when and how human resources will be brought onto and taken off the project team is called ____________.

Options:
A.

Staffing Management Plan

B.

Responsibility Assignment Matrix (RAM)

C.

Organizational Breakdown Structure (OBS)

D.

Resource Assignment Chart