Which knowledge area includes the processes to identify, define, and unify the various project management processes?

Options:
A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

PMI CAPM Premium Access
Questions 162

The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

Options:
A.

Co-location

B.

Lite-cycle

C.

Diversity

D.

Management

Questions 163

In which type of organization does the project manager have the maximum influence

Options:
A.

Centralized

B.

Composite

C.

Simple Organic

D.

Multi-divisional

Questions 164

Which of the following set of elements is part of an effective communications management plan?

Options:
A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Questions 165

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Options:
A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Questions 166

What communication methods would a project manager use for overall effective project communication?

Options:
A.

Interactive communication, push communication, interpersonal communication

B.

Interactive communication, push communication, pull communication

C.

Push communication, pull communication, interpersonal communication

D.

Pull communication, interactive communication, interpersonal communication

Questions 167

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:
A.

0.88

B.

1.12

C.

0.58

D.

1.58

Questions 168

Which statement summarizes the role of the change control board?

Options:
A.

The change control board is responsible for presenting the change for approval.

B.

The change control board will analyze the change impact in terms of cost and schedule.

C.

The change control board is responsible for managing the change management and configuration management systems.

D.

The change control board is responsible for reviewing and approving changes to the project.

Questions 169

A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

Options:
A.

The project manager should identify and deal with stakeholders only during the execution phase.

B.

Stakeholder satisfaction should be identified immediately and managed as a project objective.

C.

The project manager should focus on project objectives and deal with stakeholders as a secondary priority.

D.

Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.

Questions 170

A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?

Options:
A.

What-if scenario analysis

B.

Simulation

C.

Alternatives analysis

D.

Reserve analysis

Questions 171

What purpose does the hierarchical locus of stakeholder communications serve?

Options:
A.

Maintains the focus on project and organizational stakeholders

B.

Preserves the tocus on external stakeholders—such as customers and vendors—as well as on other projects

C.

Sustains the focus on general communication activities using email, social media, and websites

D.

Keeps the focus on the position of the stakeholder or group with respect to the project team

Questions 172

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.

Which technique is the project manager using?

Options:
A.

Three-point estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Data analysis

Questions 173

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options:
A.

Risk, resource, and communications management plans

B.

Scope, quality, and resource management plans

C.

Procurement, integration, and risk management plans

D.

Communications, schedule, and cost management plans

Questions 174

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:
A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Questions 175

An output of Control Schedule is:

Options:
A.

A project schedule network diagram

B.

A schedule management plan

C.

Schedule data

D.

Schedule forecasts

Questions 176

When is a Salience Model used?

Options:
A.

In a work breakdown structure (WBS)

B.

During quality assurance

C.

In stakeholder analysis

D.

During quality control (QC)

Questions 177

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:
A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Questions 178

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:
A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Questions 179

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:
A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Questions 180

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

Options:
A.

Program

B.

Functional

C.

Project

D.

Portfolio