Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Options:
A.

Requirements documentation

B.

Requirements traceability matrix

C.

Project management plan updates

D.

Project documents updates

PMI CAPM Premium Access
Questions 322

An output of the Develop Project Team process is:

Options:
A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Questions 323

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Options:
A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Questions 324

The Perform Quality Assurance process occurs in which Process Group?

Options:
A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Questions 325

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:
A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Questions 326

A regression line is used to estimate:

Options:
A.

Whether or not a process is stable or has predictable performance.

B.

How a change to the independent variable influences the value of the dependent variable.

C.

The upper and lower specification limits on a control chart.

D.

The central tendency, dispersion, and shape of a statistical distribution.

Questions 327

The ability to influence cost is greatest during which stages of the project?

Options:
A.

Early

B.

Middle

C.

Late

D.

Completion

Questions 328

Which tools or techniques are used in the Plan Schedule Management process?

Options:
A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Questions 329

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Options:
A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Questions 330

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:
A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Questions 331

An input used in developing the communications management plan is:

Options:
A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Questions 332

Plan Schedule Management is a process in which Knowledge Area?

Options:
A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Questions 333

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Options:
A.

Plan Procurement Management

B.

Control Procurements

C.

Collect Requirements

D.

Plan Cost Management

Questions 334

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:
A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Questions 335

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:
A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Questions 336

Which tool or technique is used in the Estimate Costs process?

Options:
A.

Acquisition

B.

Earned value management

C.

Vendor bid analysis

D.

Forecasting

Questions 337

Which process numerically analyzes the effect of identified risks on overall project objectives?

Options:
A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Questions 338

Identify Risks is part of which Process Group?

Options:
A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Questions 339

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

Options:
A.

Direct

B.

Interactive

C.

Pull

D.

Push

Questions 340

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:
A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.