Free Oracle 1z0-1057-24 Practice Exam with Questions & Answers

Questions 1

You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)

Options:
A.

Enter progress for tasks.

B.

Receive email notifications about changes that team members make to a task.

C.

View task details and the task activity stream.

D.

Edit task details.

Oracle 1z0-1057-24 Premium Access
Questions 2

While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)

Options:
A.

You usedCreate Treein the action menu.

B.

You used Create Tree Version in the action menu.

C.

You used View Tree Version in the action menu.

D.

You selected theEdit iconfor opening the hierarchy.

E.

You opened the hierarchy by clicking the name.

Questions 3

Identify theattribute of a project typethatdetermines if expenditure items are billable, and theamount type to be used as the basisfor transfer pricing. (Choose the best answer.)

Options:
A.

work type

B.

event type

C.

cost type

D.

expenditure type

Questions 4

Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)

Options:
A.

Calendar Types

B.

Project Accounting Periods

C.

Accounting Periods

D.

PA Calendar

E.

PA-GL Periods

Questions 5

Shift is one of the key elements in defining project and resource calendars.

Which two additional key elements are required to define the project and resource calendars? (Choose two.)

Options:
A.

Schedule Exceptions

B.

Workday Patterns

C.

Time off

D.

Expenditure Type

E.

Accounting Calendar

Questions 6

Your client uses Resource Breakdown Structures (RBS) and Resource Mapping to associate amounts to resources. After making some changes to the resources at project level, forecasts are regenerated. After reviewing the cost amounts associated with the resources, you suspect that the cost association does not match your client's expectations. Identify two valid rules based on which cost association works. (Choose two.)

Options:
A.

If one branch contains a user-defined resource type, precedence is given to the branch that contains a user-defined resource type.

B.

If a transaction maps to more than one level, Oracle PPM Cloud sums the precedence numbers for all resource type in the branch and gives precedence to the resource element in the branch with the highest sum.

C.

If there is only one level in RBS to which the transaction maps, the cost amounts are mapped to that level.

D.

If the sum of precedence numbers is the same for more than one branch, precedence is given to the branch with thelowest number at the lowest level.

Questions 7

Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)

Options:
A.

Create a revenue method with a revenue method classification of Amount Based.

B.

Create a revenue method with a revenue method classification of Rate Based.

C.

Create a revenue method classification with a revenue method of Percent Spent.

D.

Create a revenue method classification with a revenue method of Percent Complete.

Questions 8

Which product offering enables you to collaboratively plan and deliver projects by leveraging intuitive and integrated scheduling tools?

Options:
A.

Resource Management

B.

Project Control

C.

Project Management

D.

Project Costing

Questions 9

You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

Options:
A.

1000

B.

900

C.

800

D.

600

Questions 10

Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)

Options:
A.

Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule

B.

Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate

C.

Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule

D.

Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule

E.

Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule