There are two time driven controls in PRINCE2, which are they?

Options:

A.

Highlight and End Stage Reports

B.

Highlight and Checkpoint Reports

C.

Checkpoint and End Project Reports

D.

Highlight and Lessons Reports

Buy Now
Questions 62

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

  • Design for each month - correctly showing at public holidays and new company logo
  • Selected photographs- 12 professionally-produced photographs, showing different members of staff
  • Selected paper and selected envelope - for printing and mailing the calendar
  • Chosen label design - a competition to design a label will be held as part of this project
  • List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

  • Create the customer fast using information from the Accounts and Marketing departments
  • Confirm compliance with the Data Protection Legislation
  • Create a design for each month - this will be done by the internal creative team
  • Select and appoint a professional photographer
  • Gather photograph design ideas from previous project and agree photographic session schedule
  • Prepare a production cost forecast
  • Select paper and envelope.

Stage 3 will include the activities to:

  • Produce and select tie professionally-taken photographs
  • Hold the label design competition and choose the label design
  • Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

As the project approaches the end of stage 2, the Project Manager has requested a Product Status Account to ensure that all products are at their expected point of development. Although the list of customers has been quality reviewed, it has not been baselined because the Marketing department have not provided all of the prospective customers' details. What initial action should the Project Manager take?

Options:

A.

Delay producing the End Stage Report until the list of customers has been baselined.

B.

Raise an Exception Report to the Project Board to highlight the issue.

C.

Check the target sign-off date for the list of customers.

D.

Update the product status to baselined and obtain a commitment from the Marketing department to finish this work within the next few days.

Buy Now
Questions 63

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

  • Design for each month - correctly showing at public holidays and new company logo
  • Selected photographs- 12 professionally-produced photographs, showing different members of staff
  • Selected paper and selected envelope - for printing and mailing the calendar
  • Chosen label design - a competition to design a label will be held as part of this project
  • List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

  • Create the customer fast using information from the Accounts and Marketing departments
  • Confirm compliance with the Data Protection Legislation
  • Create a design for each month - this will be done by the internal creative team
  • Select and appoint a professional photographer
  • Gather photograph design ideas from previous project and agree photographic session schedule
  • Prepare a production cost forecast
  • Select paper and envelope.

Stage 3 will include the activities to:

  • Produce and select tie professionally-taken photographs
  • Hold the label design competition and choose the label design
  • Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

Options:

A.

The tolerances stated in the Project Plan CANNOT be changed.

B.

The Executive needs to seek formal approval from corporate management to implement this change.

C.

The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.

D.

The revision of the Project Plan would have to wait until the end stage assessment of stage 2.

Buy Now
Questions 64

Which of the following statements is TRUE with regard to expected benefits?

Options:

A.

They cannot be assigned

B.

They don't need to follow corporate objectives

C.

They should be measurable

D.

Tolerances cannot be set against expected benefits

Buy Now
Questions 65

Which of the following statements describes an outcome?

Options:

A.

Any of the projects specialist products

B.

A result of the change derived from using the project's products

C.

A measurable improvement resulting from a change

D.

Something perceived as advantages by a stakeholder

Buy Now
Questions 66

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the

recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Business options heading?

Options:

A.

The re-engineering of selected business functions would not provide the required outcome.

B.

The lack of up-to-date technology in MFH means a re-engineering of existing services will not necessarily deliver the performance improvements required.

C.

Use external consultants to provide guidance on the detailed design of the outsourced services.

D.

Set up a PRINCE2 project to deliver the outsourced services.

E.

Review a list of service providers to determine a short-list of possible service providers.

Buy Now
Questions 67

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

  • 20% discount for all repeat customers - not cost-effective and very short term
  • A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
  • A series of television and press advertisements was too expensive
  • A direct mail shot to all customers - benefit would be short term
  • Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Expected dis-benefits heading?

Options:

A.

A high quality, glossy product will involve additional costs.

B.

Individuals in the engineering team who are not selected to appear in the calendar photographs will become de-motivated.

C.

The calendar may not result in the expected 10% increase in orders.

D.

Because the Calendar project is a priority for the MNO Manufacturing Company, the delivery of other projects within the Marketing department will be delayed.

E.

The calendar may not result in the 10 further orders from the list of prospective customers in 12 months.

Buy Now
Questions 68

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run

trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Expected benefits heading?

Options:

A.

The 10-year outsourcing contract, at current prices, will be worth £80m.

B.

Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.

C.

The total expected savings over 10 years, at current prices, is £20m.

D.

The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.

E.

The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

Buy Now
Questions 69

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Timescale heading?

Options:

A.

The contract with the selected service provider will be agreed during stage 3.

B.

The expected benefits will be calculated over 10 years from completion of the project.

C.

If more MFH divisions are added to the scope of the services to be outsourced, the project timescale will be extended and the realization of benefits will be delayed.

D.

The expected benefits should start to be realized as soon as the outsourced services become operational at the end of stage 4.

E.

The transfer of equipment and staff is estimated to take six weeks.

Buy Now
Questions 70

Scenario

Additional Information

During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:

There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.

In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.

The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.

A number of alternatives were explored, including:

  • 20% discount for all repeat customers - not cost-effective and very short term
  • A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year
  • A series of television and press advertisements was too expensive
  • A direct mail shot to all customers - benefit would be short term
  • Creation of an internet website - would not suit all customers

The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.

Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.

Which 2 statements should be recorded under the Costs heading?

Options:

A.

The MNO marketing budget this year is £120k.

B.

The project will be funded from the business marketing budget

C.

10 further orders with an average profit of £2k will deliver a benefit of £20k in the first year.

D.

The new company logo is estimated to cost £4k.

E.

Project costs are estimated to be a total of £26.5k.