Questions 1

Why does the project board review the PID during an end stage assessment?

Options:
A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

PRINCE2 Prince2-Foundation Premium Access
Questions 2

Whitt is 3 purpose of the initiating a project’ process?

Options:
A.

To prepare the contract for the project to enable the project board to commit to delivery

B.

To provide the project board with Just Enough Information to decide whether to approve the Initiation stage

C.

To provide the opportunity for the senior user in confirm that they find the project product acceptable

D.

To enable the project board to empower the project manager to work within delegated authority limits

Questions 3

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

Options:
A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Questions 4

Which is an objective of the ‘directing a project’ process?

Options:
A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Questions 5

Which term is defined as the means by which an organization transitions from its current state to the target state?

Options:
A.

Change management

B.

change control

C.

Progress management

D.

Risk management

Questions 6

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

Options:
A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Questions 7

Which is a responsibility of the project board?

Options:
A.

To manage the team managers and project support

B.

To ensure production of the project's outputs

C.

To ensure effective communication with external stakeholders

D.

To implement the change control approach

Questions 8

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:
A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Questions 9

Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

Options:
A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions 10

Which is a purpose of the business case theme?

Options:
A.

To identify which role is responsible for producing the business case

B.

To identify the project's outputs

C.

To establish the controls to manage changes that may impact the project benefits

D.

To establish a viable investment proposition