Summer Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

How to Pass the PRINCE2 Prince2-Foundation Exam: Comprehensive PRINCE2-Foundation written Exam Guide and Tips

Questions 81

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Buy Now
Questions 82

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

Options:

A.

issue register

B.

issue report

C.

Issue management approach

D.

Risk management approach

Buy Now
Questions 83

Which plan should only be produced if the project is large and complex enough?

Options:

A.

Project plan

B.

Stags plan

C.

Team plan

D.

Exception plan

Buy Now
Questions 84

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 85

What is a description of a purpose of the ‘quality’ practice?

Options:

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Buy Now
Questions 86

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Buy Now
Questions 87

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

Options:

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

Buy Now
Questions 88

How is uncertainty identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 89

How do issue management and change control relate to each other?

Options:

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

Buy Now
Questions 90

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Buy Now