New Year Special 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bestdeal

How to Pass the PRINCE2 Prince2-Foundation Exam: Comprehensive PRINCE2-Foundation written Exam Guide and Tips

Questions 71

Which is a purpose of the 'controlling a stage' process?

Options:
A.

To produce a team plan for the work to be assigned to a team manager

B.

To select and implement actions that will resolve deviations from a plan within tolerance

C.

To obtain approvals for products delivered in a work package

D.

To update a project plan to incorporate the actuals from a stage plan

PRINCE2 Prince2-Foundation Premium Access
Questions 72

Which is one of the six aspects of project performance to be managed?

Options:
A.

Efficiency

B.

Timescales

C.

Estimate

D.

Work

Questions 73

Which is a minimum requirement for applying the risk theme?

Options:
A.

Threats must be assessed for their impact on the viability of the project

B.

A single role that is responsible for all risks must be defined

C.

The PRINCE2 risk management procedure must be followed

D.

Team managers must maintain their own risk registers

Questions 74

Which is a purpose of the Risk theme?

Options:
A.

Establish a method for the implementation of continuous improvement during the project

B.

Identify, assess and control problems that have occurred

C.

Provide the Project Board with a time-driven control to capture all project risks

D.

Establish a cost-effective procedure to identify, assess and control risks

Questions 75

Which is a minimum requirement for applying the plans theme?

Options:
A.

The project must have at least two management stages

B.

The team managers in the project must prepare team plans

C.

Scope tolerance must be prioritized using MoSCoW

D.

The project plan must be presented as a Gantt chart

Questions 76

Which approach must be followed as a minimum requirement for applying the plans theme?

Options:
A.

Activity-based planning

B.

Product-based planning

C.

Agile

D.

Risk management

Questions 77

Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

Options:
A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions 78

What is described as an organization's unique attitude towards risk taking

Options:
A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Questions 79

Which document should record the agreed amount of risk budget for a project?

Options:
A.

Project Brief

B.

Project Plan

C.

Risk Management Strategy

D.

Risk Register

Questions 80

Which control is time-driven?

Options:
A.

The creation of a highlight report

B.

The completion of the PID

C.

The creation of an exception report

D.

The end of the financial year