How to Pass the PRINCE2 Prince2-Foundation Exam: Comprehensive PRINCE2-Foundation written Exam Guide and Tips

Questions 31

Which role is responsible for the quality of the specialist products delivered in the project?

Options:
A.

Executive

B.

Senior user

C.

Senior supplier

D.

Project assurance

PRINCE2 Prince2-Foundation Premium Access
Questions 32

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

Options:
A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Questions 33

How many roles make up the Project Board?

Options:
A.

One

B.

Two

C.

Three

D.

Four

Questions 34

How many management stages should a PRINCE2 project consist of?

Options:
A.

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

B.

Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

C.

Initiation stage and at least one other management stage to cover the remainder of the project

D.

Start up stage, initiation stage and a closing stage

Questions 35

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Options:
A.

Only corporate or programme management

B.

Only the Project Board

C.

Only the Project Manager

D.

All levels of management

Questions 36

Which is a purpose of a Project Product Description?

Options:
A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what the project must deliver in order to gain acceptance

Questions 37

Which of the following statements about quality assurance and Project Assurance is true?

Options:
A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Questions 38

Which should be funded by a change budget?

Options:
A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Questions 39

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

Options:
A.

Progress

B.

Change

C.

Organization

D.

Quality

Questions 40

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

Options:
A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Pay for the project

D.

Specify the benefits of the project