Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

Options:
A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

PRINCE2 Prince2-Foundation Premium Access
Questions 132

How are team managers involved in tailoring PRINCE2 suit the project?

Options:
A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Questions 133

What is a purpose of the communication management approach?

Options:
A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

Questions 134

Why is it necessary to apply the 'defined roles and responsibilities' principle?

Options:
A.

Because the people involved in a project should know what is expected of them

B.

Because the project management team should be cross-functional

C.

Because the user and supplier interests should be involved on a need-to-know basis

D.

Because the project manager should represent all the stakeholders of the project

Questions 135

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE to a project:

Which role should be accountable for approving these proposals?

Options:
A.

Project board

B.

Project manager

C.

Project assurance

D.

Business layer

Questions 136

What is a risk actionee responsible for?

Options:
A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Questions 137

Which is an objective of the 'controlling a stage' process?

Options:
A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Questions 138

How does the ‘managing product delivery’ process achieve its purpose?

Options:
A.

By agreeing requirements for how project work should be undertaken

B.

By producing highlight reports to enable the project board to oversee the work

C.

By requiring the project manager to produce and monitor team plans

D.

By escalating issues and risks that cannot be resolved within stage tolerance