How to Pass the PRINCE2 Prince2-Foundation Exam: Comprehensive PRINCE2-Foundation written Exam Guide and Tips

Questions 91

Which term is defined as the means by which an organization transitions to a desired future state?

Options:
A.

Change management

B.

Risk management

C.

Issue management

D.

Communication management

PRINCE2 Prince2-Foundation Premium Access
Questions 92

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

Options:
A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions 93

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

Options:
A.

outcome

B.

exception

C.

output

D.

off-specification

Questions 94

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

Options:
A.

Risk

B.

Scope

C.

Quality

D.

Cost

Questions 95

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

Options:
A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Questions 96

Why is change management important in a project?

Options:
A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Questions 97

Which describes user's quality expectations?

Options:
A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

Questions 98

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:
A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Questions 99

Which is the BEST reason for a PRINCE? project to have at least two stages?

Options:
A.

It enables the project team to close the project in an orderly fashion

B.

it enables the project board to decide whether to proceed with the delivery of the project product

C.

It enables the project team to change the scope of the project by agreeing the impact on the business case

D.

It enables the project board to approve the appointment of external contractors, when required

Questions 100

What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

Options:
A.

Benefits sustainability

B.

Product sustainability

C.

Delivery sustainability

D.

Quality sustainability