Achieve Success in the PMI PMI-SP Exam: A Detailed PMI Scheduling Professional Guide

Questions 81

Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

Options:
A.

Risk owner

B.

Harry

C.

Project sponsor

D.

Subject matter expert

PMI PMI-SP Premium Access
Questions 82

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

Options:
A.

Power/interest grid

B.

Salience model

C.

Power/influence grid

D.

Communications matrix

Questions 83

Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement documentation and records?

Options:
A.

Records Management System

B.

Performance reporting

C.

Inspection and Audit

D.

Payment System

Questions 84

You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?

Options:
A.

Scope baseline

B.

Milestone list

C.

Project charter

D.

Project Schedule Management Plan

Questions 85

You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

PMI-SP Question 85

What is the critical path of this project?

Options:
A.

ABEHJ

B.

ACFGJ

C.

ADGJ

D.

ACFIJ

Questions 86

Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?

Options:
A.

Schedule analysis

B.

Resource leveling

C.

What-if scenario analysis

D.

Root cause analysis

Questions 87

Which of the following is an output of the Identify Stakeholders process?

Options:
A.

Scope baseline

B.

Project scope statement

C.

Project charter

D.

Stakeholder register

Questions 88

You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within the project scope. What process must you and the project team complete next in this scenario?

Options:
A.

Create the activity list.

B.

Create the WBS.

C.

Create the risk assessment.

D.

Determine the project budget.

Questions 89

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your cost variance for this project?

Options:
A.

11,667

B.

$-111,750

C.

There is no variance.

D.

$7,000

Questions 90

You are the project manager of the NHQ Project. You are coaching Alice, a new project manager, on the relationships in a project network diagram. Which relationship type between activities are the most common?

Options:
A.

SS

B.

FS

C.

FF

D.

SF

Exam Code: PMI-SP
Certification Provider: PMI
Exam Name: PMI Scheduling Professional
Last Update: Jan 24, 2025
Questions: 323