You are the project manager for your organization. Maagement has asked you for this current project. You use the critical chain method to create the project network diagram rather than the more traditional critical path method. What is the critical chain method?

Options:

A.

It examines only the non-critical path activities that are considered near critical, if the float is one day or less.

B.

It examines only the critical path activities to determine when the project completion date may be.

C.

It examines the availability of needed project resources to determine when activities may actually happen.

D.

It generates a Gantt chart that reflects the availability of project resources and considers working and non-working days for the project.

Buy Now
Questions 62

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Options:

A.

Cost, with a variance of -$8,000

B.

Schedule, with a variance of -$33,750

C.

Cost, with a variance of $278,000

D.

Schedule, with a variance of -$20,000

Buy Now
Questions 63

Donna's project has a budget at completion of $1,987,560 and she is currently 40 percent complete. Her project schedule called for her to be 45 percent complete but there have been some complications in the project. These complications have caused Donna to spend $125,000 more than what the work she has completed is worth. Based on this information what is the cost performance index (CPI) for Donna's project?

Options:

A.

86

B.

$920,024

C.

.90

D.

.86

Buy Now
Questions 64

Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Forecast by analogy

B.

Technology forecasting

C.

Autoregressive moving average

D.

Scenario building

Buy Now
Questions 65

Mark works as a project manager for BlueWell Inc. He is making relevant information available to the project stakeholders as required. According to Mark, which of the following are NOT the tools and techniques of the Distribute Information process?

Options:

A.

Communication requirements analysis

B.

Information distribution tool

C.

Communication method

D.

Communication technology

Buy Now
Questions 66

Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

Options:

A.

$1,312,504

B.

$1,979,952

C.

$1,541,544

D.

$2,474,952

Buy Now
Questions 67

You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

Options:

A.

Expert judgment

B.

Project charter

C.

Stakeholder analysis

D.

Stakeholder register

Buy Now
Questions 68

Kelly is the project manager of her organization. She is reviewing the project network diagram to confirm that the resource she has identified is available to complete the project assignments without conflicting with other activities in the project node. The availability of resources will help Kelly determine the final finish date for the project. What scheduling technique is Kelly using?

Options:

A.

Critical Chain method

B.

Resource utilization

C.

Critical Path method

D.

Resource leveling heuristics

Buy Now
Questions 69

What is the formula to find the schedule performance index?

Options:

A.

EV-PV

B.

EV/AC

C.

EV/PV

D.

EV-AC

Buy Now
Questions 70

If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?

Options:

A.

You have added lag time to the project activities.

B.

You have added management reserve to the project activities.

C.

You have added lead time to the project activities.

D.

You have added float to the project activities.

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Dec 13, 2024
Questions: 323

PDF + Testing Engine

$164.99
$66

Testing Engine

$124.99
$50

PDF (Q&A)

$104.99
$42