Achieve Success in the PMI PMI-SP Exam: A Detailed PMI Scheduling Professional Guide

Questions 51

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

PMI-SP Question 51

How much float can you use on Activity G if Activity B actually takes eight days to complete?

Options:

A.

Four

B.

Three

C.

Seven

D.

Zero

Buy Now
Questions 52

Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?

Options:

A.

Code of accounts

B.

Chart of accounts

C.

Component numbering

D.

Activity linkage sequencing

Buy Now
Questions 53

You are the project manager for the NQQ Project for your organization. You and the project team are creating the activity list for the NQQ Project. You have instructed the project team members that they should include an activity identifier and a scope of work description for each activity in the activity list. Why is this information needed?

Options:

A.

To track the work to the project requirements

B.

To maintain profit and loss statements for the project

C.

To help the project team understand what work is required to be completed

D.

To communicate the work to be completed to the project stakeholders

Buy Now
Questions 54

You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

Options:

A.

Project is behind the schedule.

B.

Costs are higher than planned.

C.

Costs are right on target.

D.

Costs are lower than planned.

Buy Now
Questions 55

What forecasting method would your project use if your project customer requires an autoregressive moving average for performance forecasting?

Options:

A.

Judgmental methods

B.

Time series method

C.

Ensemble forecasting

D.

Causal/econometric method

Buy Now
Questions 56

You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

Options:

A.

Fast tracking only works if activities can be overlapped to shorten duration.

B.

Fast tracking only works if the activities are effort-driven.

C.

Fast tracking only works if the activities are resource-driven.

D.

Fast tracking only works if activities can have start-to-start relationships.

Buy Now
Questions 57

You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to be late on reaching its milestones. What tool and technique can you use as a part of controlling the schedule to help you review various scenarios to bring the schedule into alignment with the plan?

Options:

A.

What-if scenario analysis

B.

Root cause analysis

C.

Schedule analysis

D.

Resource leveling

Buy Now
Questions 58

You work as a project manager for BlueWell Inc. Which of the following techniques will you use to determine whether particular work can best be accomplished by the project team or must be purchased from the outside sources?

Options:

A.

Contract Types

B.

Expert Judgment

C.

Procurement Negotiations

D.

Make-or-Buy Analysis

Buy Now
Questions 59

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Options:

A.

It is derived from the constraints of the project.

B.

It is assigned to the project by management.

C.

It is created by the stakeholders.

D.

It is developed from the schedule network analysis.

Buy Now
Questions 60

Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?

Options:

A.

Analogous

B.

Hanger

C.

Fragment network

D.

Parametric

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Dec 14, 2024
Questions: 323

PDF + Testing Engine

$164.99
$66

Testing Engine

$124.99
$50

PDF (Q&A)

$104.99
$42