Achieve Success in the PMI PMI-SP Exam: A Detailed PMI Scheduling Professional Guide

Questions 41

Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement?

Options:
A.

Seller

B.

Operations manager

C.

Functional manager

D.

Project manager

PMI PMI-SP Premium Access
Questions 42

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

Options:
A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Questions 43

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:
A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Questions 44

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:

PMI-SP Question 44

Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Options:
A.

32 days

B.

29 days

C.

27 days

D.

26 days

Questions 45

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

Options:
A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

Questions 46

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

Options:
A.

Work performance information

B.

Change requests

C.

Work performance measurements

D.

Forecasting method

Questions 47

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

PMI-SP Question 47
Options:
A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Questions 48

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

Options:
A.

Resource calendars

B.

Schedule data

C.

Activity list

D.

Project scope statement

Questions 49

You work as a project manager for BlueWell Inc. You have to identify the specific actions to be performed to produce the project deliverables. For this, you have to explain the three inputs for the define activities process to your project team. Which of the following is NOT a valid input?

Options:
A.

Work Breakdown Structure

B.

Enterprise Environmental Factors

C.

Scope baseline

D.

Organizational Process Assets

Questions 50

You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project. What approach would you recommend to condense the project duration?

Options:
A.

Fast tracking

B.

Crashing

C.

Effort-driven activity analysis

D.

Rewards and recognition for the project team